LEED Boundary and Complete Building Question...

NC-v4 MPR2: Must use reasonable LEED boundaries
posted by Roxanne Button on Jan 20, 2017, 7:15 pm

This may be more in line with MPR #1, but it also has to do with the LEED boundary so I'll post it here first.

We have a project that includes 4 separate structures, with 1 being on an...

Last reply: Deborah Lucking, Jan 23, 2017, 12:50 pm

Single certificate or multiple certificates?

NC-v4 MPR2: Must use reasonable LEED boundaries
posted by Ricardo Sá on Feb 1, 2017, 5:41 am

I am currently involved in the rehabilitation project of a set of school buildings located on the same grounds. The buildings are divided programmatically - classroom building, library building,...

Last reply: Tristan Roberts, Feb 15, 2017, 9:18 am

Embedded Electric Conduits Adhesive

NC-2009 IEQc4.1: Low-emitting materials - adhesives and sealants
posted by Mario S. on Feb 1, 2017, 10:10 am

Does cement adhesive for electric PVC conduits that are embedded in concrete walls has...

Last reply: Matthew Martin, Feb 3, 2017, 12:39 pm

Baseline Pumping Power

NC-2009 EAp2: Minimum Energy Performance
posted by Ahmed Labeeb on Feb 9, 2017, 8:24 am

Based on ASHRAE 90.1, the chilled water pumping power must be 22 W/gpm and does not mention the effect of pumps' head. the majority of projects that I am working on them, the proposed pumping...

Last reply: Marcus Sheffer, Feb 10, 2017, 2:22 pm

European standards for bio-based materials

EBOM-v4 MRp1: Ongoing purchasing and waste policy
posted by Ana Villarroya on Feb 24, 2017, 6:34 am

I'm working on a building's purchasing and waste policy and I'm using LEED's template. In section iv (procedures and strategies for implementation) it states that bio-based products shall meet...

Last reply: Michael Smithing, Feb 28, 2017, 12:02 pm

3 buildings that connected via link-bridge

LEED Guidance for Campuses and Multiple Buildings
posted by Michael Wahjudi on Mar 22, 2017, 12:23 am

Hi all. Wanted to seek your comments on consideration of our developments as "single building" so it can fit into one LEED certification. Our development is consists of 3 buildings that connected...

Last reply: Dave Hubka, Apr 10, 2019, 7:34 am

Scope

CI-v4 EAc5: Enhanced Refrigerant Management
posted by Michael Smithing on Mar 24, 2017, 1:52 am

For a CI project with minimal new HVAC equipment is the credit scope limited to equipment within the scope of the project only, or is there a hurdle below which...

Last reply: Dustin Stephany, Feb 17, 2022, 3:15 pm

Parking Pen

ND-v4 NPDc6: Connected and open community
posted by Ana Paula Quiros on Apr 6, 2017, 2:25 pm

Hello Eliot!

Does LEED ND prohibit having parking pens on the development main entrances???
The project is located in Mexico and is very common to have parking pens in all big...

Last reply: Eliot Allen, Apr 25, 2017, 11:05 am

CO2 monitoring for Core and Shell projects

CS-v4 EQc1: Enhanced indoor air quality strategies
posted by Irene Chung on Apr 9, 2017, 5:56 pm

Hi,

Is a copy of the lease agreement stating that tenants must install co2 sensors in all densely occupied spaces required for v4 Core and Shell projects?

If not, can the project...

Last reply: Laura Charlier, Nov 3, 2023, 2:57 pm

Option 1- Individual occupant spaces 3 level lighting

NC-v4 EQc6: Interior lighting
posted by Mario S. on Apr 11, 2017, 8:07 am

For individual occupant spaces, if the overhead lighting is controlled by an on/off switch, and each individual space is provided with an on/off task light (desk...

Last reply: Dustin Norton, Nov 19, 2018, 5:34 pm