Problem with the Quality Assurance Check Section of the MEPC

NC-v4 EAp2: Minimum Energy Performance
posted by Zeynep Cakir on Dec 19, 2018, 3:25 am

Hi everyone,

We're having problem with the Quality Assurance Check section of the MEPC v05. We write our responses to the identified issues after completing the MEPC, but when we open the...

Last reply: Marcus Sheffer, Dec 19, 2018, 9:45 am

Lab Ventillation Requirement

EBOM-v4 EAc4: Optimize Energy Performance
posted by Greg DiDomenico on Dec 19, 2018, 8:54 am

Hello All,

I am working on an energy model for a building which has labs and office spaces. For the lab spaces, we are required by the owner EHS to supply 8...

Existing Building Renovation- What to include in energy model

EBOM-v4 EAp2: Minimum Energy Performance
posted by Greg DiDomenico on Dec 19, 2018, 9:22 am

Hello All,

I am working on an energy model for major renovation on a building which has labs and office spaces. We are doing the whole building energy model in an attempt to obtain credits...

Construction Work Area Depressurization

NC-v4 EQc3: Construction indoor air quality management plan
posted by Danilo Ilic on Dec 12, 2018, 3:37 am

Does anyone have an example of how construction work area depressurization (in order to create a pressure difference between construction and clean areas) was...

Last reply: Danilo Ilic, Dec 19, 2018, 4:25 am

To use all FSC Mixed Sources label Paper, how many percentage we need fill into the Purchasing calculator field?

EBOM-v4 MRc1: Purchasing - ongoing
posted by Ray Hsing Chen on Oct 2, 2018, 10:49 pm

Regarding LEED v4 EBOM...

Last reply: Ray Hsing Chen, Dec 18, 2018, 10:23 pm

Test duration

Pilot-Credits EQpc57: Enhanced acoustical performance - exterior noise control
posted by Dionisio Franca on Dec 18, 2018, 8:16 pm

The site noise assessment must be at least 24 hours long. Is there a similar requirement for the post-construction test? The language says only "Average exterior noise level (Leq, 8h) of 45...

Lack of PPM data plus suggestions for improvement

Pilot-Credits EApc66: Community contaminant prevention - airborne releases
posted by Jamison Hill on Jul 2, 2014, 6:05 pm

Currently there exists no incentive for manufacturer's to publish PPM NOx. Although they have to do is to run some...

Last reply: Shannon Oletic, Dec 18, 2018, 3:55 pm

ASHRAE 90.1 compliance within tenancy areas

CS-v4 EAp2: Minimum Energy Performance
posted by Ricardo Sá on Dec 13, 2018, 2:13 pm

Hi, 

we are applying LEED BD+C v4 Core & Shell to a large office building. Scope of Core & Shell works inside tenancy areas:

  1. includes...

Last reply: Marcus Sheffer, Dec 18, 2018, 3:13 pm

Automatic Receptacle Control

NC-v4 EAp2: Minimum Energy Performance
posted by Jan Hesse on Aug 7, 2015, 6:36 am

ASHRAE 90.1-2010 8.4.2 states, that 50% of all 125 volt 15- and 20-Ampere receptacle outlets in private offcies, open offices and computer classrooms shall be automatically switched off when the...

Last reply: Marcus Sheffer, Dec 18, 2018, 3:08 pm

rainwater recovery at inside boundary, store at outside boundary, Can it be used as a calculation of potable water reduction?

NC-v4 WEp1: Outdoor water use reduction
posted by Ray Hsing Chen on Oct 1, 2018, 3:37 am

LEED V4 BD+C (NC) project,

Case A: Project#1-A Building, the building roof and ground recovery rainwater (inside boundary) are stored in the rainwater recovery pool outside the...

Last reply: Paula Melton, Dec 18, 2018, 11:29 am