Composite Wood Documentation

NC-v4 EQc2: Low emitting materials
posted by Vanessa Nelson on Apr 2, 2020, 12:24 pm

Is a manufacturer provided product Info sheet stating a plywood product does not contain urea formaldehyde sufficient documentation for the composite...

Green Plaque website no response and no Certificates for Projects?

NC-v4 MPR1: Must be in a permanent location on existing land
posted by Robert Fernandez on Apr 1, 2020, 4:36 pm

Hello,

Not sure where to post this but is anyone else having trouble with Green Plaque? I just received access to one of my certified projects and the congratulatory letter was formatted...

Last reply: Robert Fernandez, Apr 2, 2020, 11:55 am

Demand Controlled Ventilation

NC-v4 EAp2: Minimum Energy Performance
posted by Vassil Vassilev on Apr 2, 2020, 7:18 am

Greetings,

There is a question regarding the requirements related to DCV – 6.4.3.8 and specifically Exception 4. – “Spaces where >75% of the space design OA is required for makeup air...

Last reply: Francesco Passerini, Apr 2, 2020, 10:31 am

LEED v4.1 Renewable Energy- no contracts with a period longer than two years available

NC-v4.1 EAc5: Renewable energy
posted by J Schuetz on Apr 2, 2020, 10:30 am

Dear all,

Actually, German law prohibits electricity contracts with a fixed contract period longer than two years, there has to be the possibility to cancel the contract. Although, the...

Demand Response Metering

NC-v4 EAc4: Demand response
posted by Jordan Creveling on Apr 1, 2020, 5:42 pm

In the case of the Fully Automated Response Event Management, is the Meter that is shown providing feedback to the Utility/ISO/CSP suppose to be the Utility's Meter that comes with the Electrical...

Modeling a Greenhouse

NC-v4 EAp2: Minimum Energy Performance
posted by Gabriela Crespo on Apr 1, 2020, 6:21 pm

Hi guys!

We're working on a project that includes a greenhouse that makes up about 45% of the project's area. We found guidance on LI-5223/LI-5364, about how to treat the greenhouse as a...

Quality Views LEED Calculator- Multiple View Types, Same Space

NC-v4 EQc8: Quality Views
posted by Tahani Khalid on Apr 2, 2020, 1:54 am

When finding the area of compliance for a single room under multiple view types, does the regularly occupied space that is entered for that space change?

For example, in my project, the...

Compliance with ASHRAE 90.1- 2010- Air Tightness Query

NC-v4 EAp2: Minimum Energy Performance
posted by Quentin Jackson on Jul 18, 2017, 8:00 pm

Hi there,

I'm working on stadium in Australia. For compliance with ASHRAE 90.1-2010, the window systems (frame + glazing) have to comply with the mandatory provisions (5.4) in ASHRAE 90.1-...

Last reply: Fotis Kotsopoulos, Apr 2, 2020, 7:31 am

CO2 Monitors in correctional facilities

NC-2009 IEQc1: Outdoor Air Delivery Monitoring
posted by Peter Doo on Apr 9, 2010, 1:49 pm

Co2 monitors are required to be between 3' - 6' above finish floor. Is there any latitude in the location of these? The State Correctional Facility will not allow these to be mounted at this...

Last reply: Tyler Fenton, Apr 1, 2020, 6:55 pm

View type 3. Unobstructed views located within the distance of three times the head height of the vision glazing

NC-v4 EQc8: Quality Views
posted by Keith Robertson on Jan 8, 2018, 1:02 pm

Basic Member July 16, 2018- 12:19 pm I would also like some clarification on this point.  In another LEEDuser thread (https://leeduser.buildinggreen.com/forum/view-type-3-private-office-space), it states...

Last reply: Ryan Harrington, Apr 1, 2020, 5:04 pm