Exemption from uplight and light Trespass requirements- government-mandated roadway lighting applicable for docking area?

NC-v4 SSc6: Light Pollution Reduction
posted by Lenka Matějíčková on Mar 22, 2025, 11:45 am

Hi All,

We are working on an industrial facility (automotive plant). The area around the lorries loading/unloading docking stations is being lit by pole lighting. The lighting levels in...

District Cooling Plant- Chilled Water Metering

NC-v4 EAc3: Advanced Energy Metering
posted by Junaid Mujahid on Mar 21, 2025, 4:24 am

Hi Everyone,

For a project connected with DCP, is it sufficient to meter the chilled water coming into the project using a single BTU meter for the 'Space Cooling' end use? What if the...

PRIVATE SHUTTLE FOR A FACTORY LOCATED IN A UPCOMING INDUSTRIAL DEVELOPMENT WITH NON-EXISTANT PUBLIC TRANSPORTATION

NC-v4.1 LTc5: Access to quality transit
posted by Amal Venugopal on Jul 27, 2022, 5:13 am

The BD+C, NC project we are applying for is a factory with manufacturing unit and office spaces, located in an developing industrial  area with no mutimodel transportation facilities . The...

Last reply: Sudipta Ghosh, Mar 21, 2025, 1:51 am

Can we use both option 1 and option 2?

NC-v4 SSc2: Site development - protect or restore habitat
posted by Amanda Cunningham on Mar 20, 2025, 4:19 pm

Hello, 

Has anyone had success achieving 2 points by reaching the 15% threshold for one point and making an off-site financial support donation for a second point?

Any way to download LEED project data?

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Sustainability Ballinger on Mar 13, 2024, 5:29 pm

I'm working on creating a database of our firm's project data, specifically around our sustainability efforts.  I don't currently see any way on the LEED Online website to download in a data-...

Last reply: Sustainability Ballinger, Mar 20, 2025, 1:38 pm

Water metering of DHW in relation to Janitor's sink

NC-v4 WEc4: Water metering
posted by R Jones on Mar 19, 2025, 5:15 am

Hi LEED Users/Experts/Fellows,

I have a small office building under LEED-NC-v4.0 and I am dealing with water metering of end-uses. We selected domestic-hot-water (...

Last reply: R Jones, Mar 20, 2025, 8:23 am

Process Chiller in a Lab Building: 90.1-2019 Baseline vs. Proposed

NC-v4 EAp2: Minimum Energy Performance
posted by Kristy M. Walson on Mar 19, 2025, 6:16 pm

We're working on a 35,000 SF lab building on a campus district cooling loop. The baseline system type is #5, so there's no chilled water in the baseline. The project overcoming the process heat...

IPpc100 Passive Survivability and Functionality during Emergencies

NC-v4 INc1: Innovation
posted by Noriko Nagazumi on Jan 29, 2019, 2:44 am

Hi,

We are submitting this pilot credit via Option 2: Provide Backup Power for critical loads. The project building is office usage, but there is no instruction for office building...

Last reply: Deborah Lucking, Mar 19, 2025, 5:51 pm

IDc1.3: Safety First: Cleaning and Disinfecting Your Space

Working through COVID-19
posted by Carlos Sanchez on Dec 11, 2020, 1:53 am

I am struggling with finding the green cleaning criteria for this credit. Any help would be greatly appreciated.

Last reply: Jonathan Burgess, Mar 18, 2025, 6:02 pm

Uploading Results from Waste Audit into Arc

EBOM-v4.1 MRp3: Waste Performance
posted by Kristina K on Mar 18, 2025, 1:57 pm

Hello,

Our project completed a waste audit over a 24-hour period and the data was extrapolated to represent the whole year - the one year data was entered into Arc accordingly for the...