Equations and calc methodsEBOM-v4.1 EAp3: Energy Performanceposted by Ricardo Filho on Feb 21, 2023, 5:01 am
I am doing some research on LEED v4.1 O+M and I have a number of questions. Last reply: Saba Hajizadeh, Nov 10, 2023, 4:29 pm |
|
Estimating Energy Performance Scores before registering a projectEBOM-v4.1 EAp3: Energy Performanceposted by Bob Snow on Jan 10, 2023, 10:37 amSamuel Sura Mr SALVIS LEEDuser Premium Member 3 thumbs up September 26, 2023- 7:46 am Hi Bob, I found this information on a different Leeduser forum: Here's an update in case anyone comes across this old thread: it's now free to create your project in Arc and see your performance without paying to register anything. From < https://leeduser.buildinggreen.com/forum/black-box-or-transparent-benchmarking > Samuel Log in or register to post comments ... Last reply: Samuel Sura, Sep 26, 2023, 7:46 am |
|
Renewable energyEBOM-v4.1 EAp3: Energy Performanceposted by SAMY Chamy on Jun 23, 2023, 9:16 am
Hi Team, We have received an inquiry from a large corporation with more than 20 buildings on the same campus that has 2.5 MW of solar on its roof and operates with net metering (... |
|
Manufacturing energy and water consumptionEBOM-v4.1 EAp3: Energy Performanceposted by Salomee Hinque on Jun 8, 2023, 11:34 pm
Dear all, I have a manufacturing project which is LEED BD+C certified and going for recertification under LEED O+M v4.1. On the ARC platform, does the energy and the... Last reply: Dave Hubka, Jun 13, 2023, 9:41 pm |
|
GHG emission factor- renewable energy and operating hours-EA energy performance O+M v4.1EBOM-v4.1 EAp3: Energy Performanceposted by RICCARDO BALLESIO on May 18, 2023, 6:30 am
Hello everyone, in the previous version LEED... |
|
LEED O+M Campus Chiller PlantEBOM-v4.1 EAp3: Energy Performanceposted by Rajarajan Sekar on Mar 11, 2023, 1:47 am
We are trying to go for LEED O+M certification in one of our buildings which has a Chiller plant in it along with other occupied places Since we are measuring the building energy... |
|
Can start of 365 data collection period be retroactive?EBOM-v4.1 EAp3: Energy Performanceposted by Susan Di Giulio on Jan 24, 2023, 12:16 am
Hi, We have a client that wishes to start on LEED O+M immediately but needs to complete certification before the end of year (12/31/2023) for ESG reporting reasons. Assuming that their... Last reply: Ricardo Filho, Feb 8, 2023, 7:05 am |
|
Greenhouse Gas Emissions CalculatorEBOM-v4.1 EAp3: Energy Performanceposted by Heather Enos-Graves on Nov 19, 2021, 2:10 pm
Hello, Can anyone suggest an accurate and reliable calculator for greenhouse gas emissions? Thank you Last reply: Saba Hajizadeh, Jun 24, 2022, 8:56 am |
|
Outside Temperature Adjustment FactorEBOM-v4.1 EAp3: Energy Performanceposted by Julie Hendricks on Nov 9, 2020, 11:44 pm
The calculation for determining the outside temperature adjustment factor in the... Last reply: Francisca Gonzalez, Jun 15, 2022, 5:58 pm |
|
LEED v4.1 EB O&M: How can data center projects overcome the constraints of the Arc energy score?EBOM-v4.1 EAp3: Energy Performanceposted by JL on Mar 14, 2022, 5:25 pm
For LEED v4.1 EB O&M projects, I understand that Energy Performance scores are assigned in the Arc platform by considering a building's floor area, occupancy, and operating hours. And that... |