Arbitrage optionCS-v4 EAc5: Renewable energy productionposted by Glen Boldt on May 17, 2024, 7:09 pm
When using the "arbitrage" option, is there a limit regarding where, geographically, the replacement RECs can be purchased form? Within the USA, do they need to be purchsed from a renewable... Last reply: Marcus Sheffer, May 17, 2024, 7:35 pm |
|
Multi-building project- installing renewables on only 1 buildingCS-v4 EAc5: Renewable energy productionposted by Shannon Oletic on Jul 5, 2023, 2:56 pm
We have a multi industrial building project (3 buildings) registered through a Campus Approach (as opposed to Group approach). Is it acceptable to install the rooftop solar PV system on only one... Last reply: Shannon Oletic, Mar 20, 2024, 9:55 am |
|
Do we need to included tenant area in renewable energy calculation for CS building?CS-v4 EAc5: Renewable energy productionposted by Yoyo Shek on Feb 9, 2023, 10:45 pm
Dear All, We are doing a LEEDv4 CS project and I am not sure whether those tenant controlled areas such as shop and office are required to include in the calculation of %... Last reply: Marcus Sheffer, Mar 13, 2023, 3:35 pm |
|
RE: v.4 Core & Shell- RECs as Offsite PowerCS-v4 EAc5: Renewable energy productionposted by Yoyo Shek on Feb 9, 2023, 11:06 pm
Hi LEED user, We have a C&S project includes retail and office towers with limited space for renewable power generation. The utilities company in the area has just launched... Last reply: Marcus Sheffer, Feb 10, 2023, 3:43 pm |
|
Solar panels outside LEED boundaryCS-v4 EAc5: Renewable energy productionposted by Jefferson Au-Yeung on Jan 14, 2022, 12:20 pm
Hi My project is a mixed use complex with two towers sitting on top of a seven storey podium. Only the podium would pursue LEED certification. If we place solar panels on top of the two... Last reply: Marcus Sheffer, Jan 14, 2022, 2:21 pm |
|
Future renewable energy within the leed borderCS-v4 EAc5: Renewable energy productionposted by Instra Ingenieros on Sep 30, 2019, 11:31 am
Hi! We have a project that the owner want to deliver the LEED documentation at the end of 2019. The project will have an a huge quantity of photovoltaic energy in the roofs of the... Last reply: Instra Ingenieros, Jun 3, 2020, 9:27 am |
|
Exemplary Performance- available or not available for CS?CS-v4 EAc5: Renewable energy productionposted by Eva-Maria Schliebs on Oct 14, 2019, 5:17 pm
Hello, Could you please give me some insight about the exemplary performance credit CS-v4 EAc5 for... |
|
Core and shell building’s energyCS-v4 EAc5: Renewable energy productionposted by Devendra Chaughule on Jun 27, 2019, 10:34 am
Dear All, We are doing a LEEDv4 CS project. For applying this credit, we need to engage 50%-100% (1-2 points) of total energy to be addressed by... Last reply: Marcus Sheffer, Jun 27, 2019, 11:11 am |
|
Definition of "utility service area"CS-v4 EAc5: Renewable energy productionposted by Helena Larsson on Sep 13, 2017, 9:42 am
Hi, Can you please provide som insight as to what "utility service area" refers to? Within the city limits or is there another way to define this a bit clearer. Kind regards ... Last reply: Gail Hampsmire, Feb 12, 2018, 4:16 pm |
|
Renewable Energy Consumption Scope for Core & ShellCS-v4 EAc5: Renewable energy productionposted by Kristina Pobre on Nov 19, 2017, 10:15 pm
The credit requires to aggregate at least 1% of the project energy consumption based on EAp Min Energy Performance. For C&S, projects do we calculate the 1% of the WHOLE (including tenant... Last reply: Marcus Sheffer, Nov 20, 2017, 10:26 am |