posted by Helena Larsson on Sep 13, 2017, 9:42 am

Hi,

Can you please provide som insight as to what "utility service area" refers to? Within the city limits or is there another way to define this a bit clearer.

Kind regards

...

Last reply: Gail Hampsmire, Feb 12, 2018, 4:16 pm

Renewable Energy Consumption Scope for Core & Shell

CS-v4 EAc5: Renewable energy production
posted by Kristina Pobre on Nov 19, 2017, 10:15 pm

The credit requires to aggregate at least 1% of the project energy consumption based on EAp Min Energy Performance. For C&S, projects do we calculate the 1% of the WHOLE (including tenant...

Last reply: Marcus Sheffer, Nov 20, 2017, 10:26 am

wood that is not waste is eligible?

CS-v4 EAc5: Renewable energy production
posted by Jens Apel on Sep 6, 2017, 5:17 am

I am not quite sure if this is the USGBC's intent, and maybe I'm a nitpicker, but:

-Biofuel "(in some cases)" is eligible, the "some cases" are not further described

-ineligible...

Last reply: Marcus Sheffer, Sep 6, 2017, 12:07 pm

PPA as renewable energy production?

CS-v4 EAc5: Renewable energy production
posted by Lai-San wong on Jun 12, 2017, 9:38 am

Hi!

In the requirement for EAc5 (BD+C) it is stated:
"The use of solar gardens or community...

Last reply: Marcus Sheffer, Aug 28, 2017, 9:41 am

PV System on Campus Project

CS-v4 EAc5: Renewable energy production
posted by Annalise Reichert on Jan 23, 2017, 6:18 pm

I am working on a Campus project that consists of 3 Core and Shell office buildings and 1 parking garage. Each building will be built in a different phase, therefore we aren't able to pursue...

Last reply: Marcus Sheffer, Jan 24, 2017, 10:16 am

LEED v4 BD+C- Core and Shell: Renewable energy production

CS-v4 EAc5: Renewable energy production
posted by Spyridon Kostopoulos on Sep 28, 2015, 10:46 am

Can anyone clarify for me please if for a Core and Shell certification, the total building energy costs would pertain only to those building installations which the developer controls and not...

Last reply: Marcus Sheffer, Sep 30, 2015, 1:03 pm

District heating cooling plant off-site

CS-v4 EAc5: Renewable energy production
posted by Mike D on Aug 7, 2014, 4:00 am

Under the LEED Core & Shell Version 4, the project will be connected to a district heating and cooling plant. Can this be claimed as a...

Last reply: Marcus Sheffer, Apr 14, 2015, 10:08 am