Topic | Recent |
---|---|
Previous Buildings Demolition activitiesNC-v4.1 MRc5: Construction and demolition waste managementposted by Carla Joan Carrasquillo on Jun 23, 2023, 9:55 am
I'm working with a project that comprehends various buildings (~20), from which only 10 will be certified. The complexity of the project is related to the demolition activities that will take... Last reply: Dave Hubka, Apr 22, 2024, 3:28 pm |
|
Innovative StrategiesPilot-Credits SSpc154: Heat Island Mitigation with Cool Wallsposted by Dulce Solis on Apr 22, 2024, 2:31 pm
Has anyone utilized innovative design approaches or unique cool wall materials for Heat Island Mitigation (SSpc154)? We're interested in learning about any unconventional... |
|
Optimizing Cool Wall DesignPilot-Credits SSpc154: Heat Island Mitigation with Cool Wallsposted by Dulce Solis on Apr 22, 2024, 2:26 pm
What strategies or design considerations have you found effective in maximizing the heat island mitigation benefits of cool walls while minimizing potential negative impacts such as glare,... |
|
Measuring SuccessPilot-Credits SSpc154: Heat Island Mitigation with Cool Wallsposted by Dulce Solis on Apr 22, 2024, 2:23 pm
How have you evaluated the performance and effectiveness of cool walls in mitigating the urban heat island effect within your projects? What monitoring tools, metrics, or post-occupancy... |
|
Outlining the need, importance, and training framework for cleaning operativesLEED v5 O&M Existing Buildings Public Commentsposted by Lawrence Boodasingh on Apr 21, 2024, 12:20 pm
Janitorial and custodial services play a crucial role in maintaining the cleanliness, hygiene, and overall functionality of buildings, particularly in the context of sustainable practices such as... |
|
Can the Shower Rooms be included in the Tenant's Sale Lease Agreement?CS-v4 LTc6: Bicycle facilitiesposted by Nadia Garcia on Apr 18, 2024, 3:59 pm
Hello LEED community, I'm seeking clarification regarding the Bicycle Facilities credit requirements in LEED v4 BD+C: Core & Shell, specifically regarding the inclusion of shower... |
|
IN- GREEN BUILDING EDUCATIONCS-v4 INc1: Innovationposted by Dulce Solis on Oct 30, 2023, 12:29 pm
Has anyone implemented the second strategy in the guide "The development of a manual, guideline or case study to inform the design of other buildings based on the successes of this project."?... Last reply: emily reese moody, Apr 18, 2024, 3:58 pm |
|
CONSTRUCTION WASTE HEATED FOR CLINKER PRODUCTION, COUNTED AS WASTE DIVERSION?NC-v4 MRp2: Construction and demolition waste management planningposted by Olga Yuil on Apr 15, 2024, 3:55 pm
For a project located in Central America, construction waste is used for clinker production. For this purpose, construction waste is heated to temperatures above 900C. According to those... |
|
Percentage of occupancy for the Indoor Water Use Reduction Calculator for the prerequisite- project only has ADA restrooms.CI-v4 WEp1: Indoor water use reductionposted by Laura Castro Montoya on Mar 27, 2024, 7:39 pm
Currently, I am conducting certification for an office project, in the commercial interiors mode, which only has ADA restrooms within the LEED boundary. The majority (95%) of users will be using... |
|
Collected rainwater used for flush fixtures (toilets)CS-v4.1 SSc4: Rainwater managementposted by Sofía Rizo on Mar 26, 2024, 3:26 pm
The new v4.1 requirements for credit Rainwater Management - option 1, state that "The percentile event volume must be retained (i.e. infiltrated, evapotranspirated, or collected and... |