EBOM-v4.1 EAc1: Energy Performance
posted by Vanni arasan on Mar 23, 2020, 11:24 am

I am working on LEED v4.1 EB O&M Datacenter rating system, I haven't getting Energy Performance score.  Please advise how to enter the energy data i.e., Whole Facility Energy Consumption...

Leed ap in innovation credit

NC-v4 INc2: LEED Accredited Professional
posted by Vidya Thota on Feb 8, 2018, 10:37 pm

What are the roles of leed ap in the project?

Last reply: David Hubka, Mar 18, 2020, 11:49 am

Minimum IAQ performance monitoring requirement

NC-v4 EQp1: Minimum indoor air quality performance
posted by sonali rajwade on Feb 22, 2019, 1:52 am

We are having query related to prerequisite requirement of monitoring in LEED BD+C V4. 

We are planning to install 'Direct Evaporative cooling system' with HVLS (high volume low speed)...

Last reply: Dang Thi, Feb 25, 2020, 4:37 am

Enhanced Commissioning V4

NC-v4 EAc1: Enhanced Commissioning
posted by Prakash Sekar on Feb 1, 2020, 5:15 am

Can u share the sample submittal document for Enhanced Commissioning V4

How to draw the 11 degree line to calculate unobstructed view

Healthcare-v2009 IEQc8.2: Daylight and views - views
posted by P Hariharan on Apr 26, 2016, 1:29 am

as possible.. Log in or register to post comments Ghaith Moufarege EcoConsulting LEEDuser Premium Member 877 thumbs up May 3, 2016- 8:45 am Please provide me with email, as it is not possible on forum, Thanks Log...

Last reply: Irene Chung, Jan 4, 2020, 11:47 am

Modeling Evaporative cooling systems (ambiator)

NC-2009 EAp2: Minimum Energy Performance
posted by Visu Boj on Sep 29, 2015, 3:26 am

Hi all,
Iam modelling ambiator for a factory building in India. My baseline system is Packaged...

Last reply: Marcus Sheffer, Dec 22, 2019, 5:24 pm

Exterior Lighting control for 24x7 operating building

NC-v4 EAp2: Minimum Energy Performance
posted by Rathnashree Bharadwaj on Jul 27, 2018, 2:28 am

We have a commercial building which is 24x7 operating. How do we comply with the 9.4.1.7 b., 9.4.1.7c requirements when the building does not have any business closing or business opening hours...

Last reply: Waleed AlGhamdi, Dec 10, 2019, 11:22 am

Water discharge into Municipal STP

EBOM-v4.1 WEc1: Water Performance
posted by Kumar Biplab on Sep 10, 2019, 6:07 am

Background:- The building is part of a planned township and the township is maintained by municipality. Municipality also supplies potable water to the building through metered connection. During...

LEED v4-Credits MR-USGBC approved program

CI-v4 MRc3: Building product disclosure and optimization - environmental product declarations
posted by Dipti Talwar on Feb 3, 2016, 4:45 am

Dear all,
about MRc3 in LEED v4, could I have more information or links where can I find information especially about USGBC approved program?
Thank you in advance!

Last reply: Megan Recher, Jul 22, 2019, 3:38 pm

Basic Amenities Within the Main Building

CI-2009 SSc2: Development Density and Community Connectivity
posted by Aswin M on Dec 31, 2015, 2:01 am

We have a Retail Commercial Interior project inside a Main building. The Main building has many amenities such as restaurant,library, departmental stores, beauty salon, etc,. which are open to...

Last reply: Ranya Metwalli Shields, Jul 7, 2019, 6:56 am