Factory-Existing Building

EBOM-v4 EAp2: Minimum Energy Performance
posted by VISHESH AGARWAL on Aug 19, 2016, 6:04 am

I am working on the factory existing building project. the machine load is about 3000 kw. when i put all the electricity and other consumption data into energy star portfolio manager and i am...

Last reply: Vishesh Agarwal, Jan 11, 2019, 1:53 am

China mosaic tiles

NC-2009 SSc7.2: Heat island effect - roof
posted by jesmin joseph on Jan 31, 2017, 3:52 am

In a Project,we have used china mosaic tiles in 100% of the...

Last reply: shawn jang, Dec 2, 2018, 11:10 pm

No maximum parking mentioned in local byelaw

CI-v4 LTc5: Reduced parking footprint
posted by Prakash Sekar on Nov 5, 2018, 7:17 am

Hi all!

LT Credit - Reduced parking footprint

Our state bye law does not mention any limit for maximum parking. but the parking requirement meets the baseline criteria of LEED. how...

Last reply: Emily Purcell, Nov 5, 2018, 1:50 pm

Fresh air in Tenant Lease Agreement

CS-v4 EQp1: Minimum indoor air quality performance
posted by Nandana Kumar on Oct 16, 2018, 8:09 am

Hi,

We are working in a Core & Shell project where the project owner has decided to provide only Chillers n Pumps to the tenant. Whereas...

Last reply: Ammon Palmer, Oct 16, 2018, 10:23 am

Modeling the non project area

CI-v4 EAp2: Minimum Energy Performance
posted by Rathnashree Bharadwaj on Aug 9, 2018, 7:17 am

Hello,

We have a G + 7 floor building in which the client is occupying only 5th, 6th and 7th floor. Dedicated VRF systems are provided for these floors. In such a scenario, we can model...

Last reply: Marcus Sheffer, Oct 10, 2018, 11:09 am

Energy cost for Baseline and proposed case CHP system

NC-2009 EAp2: Minimum Energy Performance
posted by SAMY Chamy on Sep 26, 2018, 3:09 am

Dear All

Our project uses a...

Last reply: David Eldridge, Sep 28, 2018, 12:50 pm

Humidification Plant load

NC-2009 EAp2: Minimum Energy Performance
posted by SAMY Chamy on Sep 26, 2018, 2:59 am

Dear All:-

We have large manufacturing facility with Humidification plant & Chiller

The Electrical load of this Humidification plant is about 3000 kW (supply, return fan, Water...

Last reply: Marcus Sheffer, Sep 26, 2018, 9:34 am

Publicly Available- Informal Transit

EBOM-v4 LTc1: Alternative Transportation
posted by Nandana Kumar on Aug 30, 2018, 2:34 am

Trista Little Sustainability Manager, WSP USA LEEDuser Expert 340 thumbs up August 30, 2018- 12:51 pm Hi Nandana, I'm not able to locate that table in the Reference Guide. Is this an EBOM question or an NC question? If it's NC, I recommend re-posting to that forum. Thanks! Log in or register to post comments Nandana Kumar Deputy General Manager, LEAD Consultancy & Engineering Services LEEDuser Basic Member 6 thumbs up August 31, 2018- 1:15 am Dear Trista, Thank you for your response. The table is available on LEED V4 EB O&M Reference guide under 'Transportation...

Last reply: Trista Little, Sep 5, 2018, 4:41 pm

Using RCR calculation in an open office.

NC-v4 EAp2: Minimum Energy Performance
posted by VEL MUTHU on Jul 30, 2018, 1:37 pm

All, 

I am currently working on a office facility/building. When i tried to do the...

Last reply: Marcus Sheffer, Jul 30, 2018, 4:12 pm

Use of Recharge Pits for credit compliance

EBOM-v4 SSc2: Rainwater management
posted by Aarti Dhar on Jul 28, 2018, 11:08 am

Will the Use of Rainwater recharge pits comply with the credit requirement?