When using the "arbitrage" option, is there a limit regarding where, geographically, the replacement RECs can be purchased form? Within the USA, do they need to be purchsed from a renewable source within the same state as the project?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5912 thumbs up
May 17, 2024 - 7:35 pm
No they don't need to be from the same state or even region of the country.