Hi!

We have a project that the owner want to deliver the LEED documentation at the end of 2019. The project will have an a huge quantity of photovoltaic energy in the roofs of the buildings but the installation is expected to finish for the 3rd quarter of 2020.

Is any posibility to reclaim the points of this photovoltaic system with a written commitment that it will be installed, or a contract of the installation?

 

Thanks you in advance

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 10/01/2019 - 21:07

I think it has to be installed.

Wed, 06/03/2020 - 08:25

Hi Angel!! I am having the same problem... Did you figure out how to proceed? Did you take credit from the "future photovoltaic system"? Thanks in advance!

Wed, 06/03/2020 - 13:27

Hi Maria, Since the commissioning should include the renewable energy in the scope, we have to wait to deliver the documentation until the photovoltaic system is constructed. Regards