Log in
Forum
Topic

LPD

NC-2009 EAp2: Minimum Energy Performance
posted by Leandro Silva on May 10, 2013, 2:05 pm

When calculating...

Last reply: Cory Duggin, Mar 14, 2023, 10:40 am

Core and Shell selection- Question

LEED Rating System Selection
posted by Konstantina Kalliakoudi on Mar 13, 2023, 12:24 pm

Hello to all LEED users,

I have a project which is a new construction of an Office building. The Owner will rent each floor to tenants. Each Floor    will be designed as an Open...

Last reply: Dave Hubka, Mar 14, 2023, 7:56 am

Modeling Toilet exhaust fans

NC-2009 EAp2: Minimum Energy Performance
posted by Matt Scott on Nov 5, 2013, 11:55 am

Let's say you have a proposed zone being conditioned by an RTU with only a supply fan and you also have a small exhaust fan exhausting air directly from a toilet room, and that's the extent of...

Last reply: Julio Fernandez Amodia, Mar 14, 2023, 4:49 am

Plug loads for server rooms

NC-2009 EAp2: Minimum Energy Performance
posted by MARCIO OROFINO on Apr 22, 2015, 4:39 pm

Hi.
I am working for this project - a small one-floor office building, which has a 14 m2 server room. The project for the server room has not been developed yet - there will be a specific...

Last reply: Jean Marais, Mar 14, 2023, 4:39 am

Documentation for No Cooling Tower

Pilot-Credits WEpc94: No Cooling Tower
posted by Marelle Davey on Feb 2, 2022, 6:37 pm

that you participated in the LEEDuser forum, and completed the USGBC feedback survey. Log in or register to post comments 0 Vote up! Hi Talia, I didn't know that this credit is closed for new...

Last reply: Konstantina Kalliakoudi, Mar 14, 2023, 4:20 am

Do we need to included tenant area in renewable energy calculation for CS building?

CS-v4 EAc5: Renewable energy production
posted by Yoyo Shek on Feb 9, 2023, 10:45 pm

Dear All,

We are doing a LEEDv4 CS project and I am not sure whether those tenant controlled areas such as shop and office are required to include in the calculation of %...

Last reply: Marcus Sheffer, Mar 13, 2023, 3:35 pm

Warehouse ventilation filtration system

Warehouses-NC-v4 EQp1: Minimum indoor air quality performance
posted by Gabriela Mena on Nov 24, 2020, 1:53 pm

I am working on a warehouse project that has supply fans (wall mounted) to ventilate the space, we are pursuing the Enhanced...

Last reply: Dave Hubka, Mar 11, 2023, 11:12 pm

Option F: If furniture is included...

NC-v4 EQc6: Interior lighting
posted by John Mlade on Mar 9, 2023, 3:14 pm

Hi all,

Curious if it may be possible to consider furniture and pursue Option F if furniture is NOT included in other credit calculations. In our case, the building will be furnished by...

Last reply: Dave Hubka, Mar 11, 2023, 11:04 pm

Integrative Process Facilitator

LEED v4.1 Discussion Forum
posted by Edward Reifenstein on Mar 9, 2023, 6:39 pm

Nadav Malin President BuildingGreen, Inc. LEEDuser Moderator 834 thumbs up March 9, 2023- 8:02 pm Hi Edward, USGBC isn't specific about this but, in my experience, the facilitator can be either a member of the design team or someone engaged specifically to facilitate this process. You might also want to repost this question to the LEEDuser forum for that specific credit and see what the people there have to say. Good luck! Log in or register to post comments Dave Hubka Practice Leader- Sustainability EUA LEEDuser Expert 418 thumbs up March 11, 2023- 10:53 pm It is my opinion that an experienced LEED...

Last reply: Dave Hubka, Mar 11, 2023, 10:53 pm

Food Service Equipment

CI-v4 EAc5: Enhanced Refrigerant Management
posted by ESD Engineer on Mar 22, 2016, 5:30 pm

For a LEEDv4 CI project, does food service equipment such as ice cube machines, ice machines, and chiller freezers need to be documented?

Last reply: Dave Hubka, Mar 11, 2023, 10:50 pm