Forum » NC-v4.1 LTc8
Topic
Replies
Recent

Combination option?

NC-v4.1 LTc8:Electric Vehicles
posted by  Joseph Snider  on 

Has anybody seen an option to install some EVs and then some EV ready to combine Option 1 and 2?  In 2009, there was a way to run weighted calcualtions.  We have a project doing a little

8
Energy Engineer
ads ENGINEERS, DPC
LEEDuser Basic Member
21 thumbs up
Wed Dec 10, 2025, 9:38 pm

“Connected Functionality Criteria for ENERGY STAR” for EVSE

NC-v4.1 LTc8:Electric Vehicles
posted by  JONGYEON WON  on 

Hello all,
I’d like to confirm the exact requirements for this credit.

0

EV Vehicle Signage and ability to combine with Handicap Parking

NC-v4.1 LTc8:Electric Vehicles
posted by  Summer Gorder  on 

We have a County project that would like to combine EV with Handicap parking. Can that contribute toward the 5%?

0

Number of spaces

NC-v4.1 LTc8:Electric Vehicles
posted by  Norman Sutton  on 

I have a site with 124 parking spaces.  For Option 1 the math points to needing 6.2 spaces (.05 x 124).  To earn the credit, will chagring stations for 6 spaces be enough, or will 7

2
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Tue Dec 10, 2024, 2:45 pm

Connected Functionality Criteria

NC-v4.1 LTc8:Electric Vehicles
posted by  Rebecca Hatchadorian  on 

Can anyone give me a better understanding of the "Connected Functionality Criteria" requirement?

2
Sustainability Lead
Parkhill
LEEDuser Basic Member
11 thumbs up
Thu Sep 19, 2024, 4:43 pm

EV space accessibility

NC-v4.1 LTc8:Electric Vehicles
posted by  Lawrence Rennell  on 

Do all EV spaces required to be available to the general public?

3
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Wed Mar 13, 2024, 3:36 pm

Off-street parking provided is less than minimum required spaces for EV-ready.

NC-v4.1 LTc8:Electric Vehicles
posted by  Erica Downs  on 

Our project only has 5 parking spaces (all off street), and these are for employees only (FTE = 6), including one HC space. 

4
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Fri Mar 1, 2024, 3:52 pm

EVSE and ADA parking spaces

NC-v4.1 LTc8:Electric Vehicles
posted by  Bryna Dunn  on 

Has anyone submitted a project that includes ADA spaces in the spaces served by EVSE?  For example, if a total of 3 charging stations are required on a project, and one of those is placed at a

6
Sustainable Design Lead
CannonDesign
LEEDuser Expert
379 thumbs up
Thu Nov 10, 2022, 6:52 pm

Preferred Parking for Electric Vehicles

NC-v4.1 LTc8:Electric Vehicles
posted by  Catherine Blakemore  on 

Do the electric vehicle parking spaces need to be located within a certain distance of the building entrance?  If yes, what is maximum allowable distance and is this distance a radial distance

2
Mon Nov 7, 2022, 2:36 pm

Electric Vehicles Option 1 requirements

NC-v4.1 LTc8:Electric Vehicles
posted by  Olivera Nikolic  on 

Could you please advise if the below interpretation of LTc8 credit/ Option 1 is correct:

0

Are all project parking spaces to be included in the count for an Addition, or just the new spaces designed for the Addition?

NC-v4.1 LTc8:Electric Vehicles
posted by  Mollie O'Rourke  on 

We have a project with a 4-story horizontal addition being added (it is actually a healthcare facility, but there are not currently any Q/A's in the HC Forum).  Being helathcare, there is a la

3
Sustainability Consultant
Stantec
LEEDuser Premium Member
25 thumbs up
Tue Apr 12, 2022, 4:34 pm

Project with no parking

NC-v4.1 LTc8:Electric Vehicles
posted by  Summer Gorder  on 

Can you still earn this credit with a project with no parking?

1
Mon Feb 28, 2022, 1:33 pm

electric vehicles and reduced parking footprint?

NC-v4.1 LTc8:Electric Vehicles
posted by  Craig Flandermeyer  on 

Is there a way in v4.1 to use these two credits in tandem?  V4 has some guidance that increases percentages if both are used.  Curious if anyone has attempted both.

1
Wed Mar 23, 2022, 5:53 pm

Electric Vehicle -required project documentation

NC-v4.1 LTc8:Electric Vehicles
posted by  Michelle DeLora  on 

I have a client asking me about Option 2 - which is ESVE ready for 10% of parking. In the online summary of the credit it does not go into the required uploads.

1
Mon Feb 14, 2022, 7:21 pm

Signage for EV spaces

NC-v4.1 LTc8:Electric Vehicles
posted by  Amanda Polematidis  on 

For those of you who completed the credit, would one sign for an area with EV charging stations suffice, or does each charging station need a sign?

2
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Mon Dec 6, 2021, 6:08 pm

Option 1: 2% or 5%, Option 2: 6% or 10%?

NC-v4.1 LTc8:Electric Vehicles
posted by  Timothy Ian Middleton  on 

Thanks to LEED User I just discovered the latest version of NC4.1_LTc8 requires 5% of spaces to comply with Electric Vehicle Charging Requirements, instead of 2%.

6
Mon Sep 27, 2021, 6:56 am

Level 1 EV chargers - any credit for extensive installations vs a few Level 2's?

NC-v4.1 LTc8:Electric Vehicles
posted by  Pooja Sannamani  on 

Does anyone have any experience in getting credit for more Level 1 chargers?  Increasing having clients question whether Level 2 is the right approach for mass rollout due to electrical infras

1
Fri Sep 17, 2021, 3:40 pm
1
Thu Aug 19, 2021, 1:12 pm

EV spaces for residential portion?

NC-v4.1 LTc8:Electric Vehicles
posted by  MARLOES REININK  on 

We have a mixed-use project (office, hotel, & residential apartments). With this credit now specific to EV spaces only, how are the residential occupant spaces addressed?

1
Tue Jul 6, 2021, 4:12 pm

EV charging for spillover parking

NC-v4.1 LTc8:Electric Vehicles
posted by  Deborah Lucking  on 

Our project has allocated areas for spillover parking (used a few times a year) in ones and twos around the site, accessible from an alley. much like on-street parking.

1
Tue May 4, 2021, 7:31 pm

EV parking space distribution

NC-v4.1 LTc8:Electric Vehicles
posted by  Nadia Bini  on 

Our project has both employee parking and visitor parking.

1
Wed Nov 11, 2020, 9:49 pm

EV Ready - Raceway

NC-v4.1 LTc8:Electric Vehicles
posted by  Jill Kurtz  on 

We have a project that is seeking certification. It shares parking with existing buildings on its campus.

1
Tue Nov 3, 2020, 9:20 pm

On-site EV required if only off-site parking provided?

NC-v4.1 LTc8:Electric Vehicles
posted by  Rebecca Aarons-Sydnor  on 

The first line of the credit states the criteria as "Provide charging infrastructure for electric vehicles for on-site parking." However, under Option 1, it refers to "all parking spaces used by pr

1
Tue Sep 15, 2020, 12:52 pm

v4.1 Interpretation - Are spaces required to be "preferred"?

NC-v4.1 LTc8:Electric Vehicles
posted by  Brian Salazar  on 

Hello!  I asked this question under v4.1 Schools, but this side of the world seems better traveled.  

2
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Mon Aug 31, 2020, 6:46 pm
3
Default Avatar
Global Green Building Program Manager
Intel Corp
LEEDuser Basic Member
1 thumbs up
Mon Aug 31, 2020, 4:15 pm

"in close proximity"

NC-v4.1 LTc8:Electric Vehicles
posted by  emily reese moody  on 

Anyone have any guesses as to what the acceptable proximity is to meet this portion of the requirements?

4
CPC, LEED AP BD+C
Durotech, Inc.
LEEDuser Basic Member
3 thumbs up
Wed Jul 29, 2020, 4:34 pm
2
Sustainable Design Lead
CannonDesign
LEEDuser Expert
379 thumbs up
Wed Jul 29, 2020, 3:55 pm

Infrastructure vs EVSE Install, can we get points for both for a total of 2 points?

NC-v4.1 LTc8:Electric Vehicles
posted by  Derick Farfan  on 

Still learning...the way the credit is written it makes it appear that it is you go EITHER go for the Infrastructure Credit (6% or 6 spaces, whichever is greater) OR EVSE Install (2% or 2, whicheve

0

Exemplary Performance for Electric Vehicles

NC-v4.1 LTc8:Electric Vehicles
posted by  Michelle Lambert  on 

Is Exemplary Performance available for installing more electric vehicle charging stations than the required 2% in v4.1?

1
Wed Jun 3, 2020, 7:23 pm

EVSE - ISO 15118 compliance

NC-v4.1 LTc8:Electric Vehicles
posted by  Mike Cavanaugh  on 

I'm looking into substituting this credit and pursuing option 1 (2% of spaces) but have a question about the third criteria for EVSE - Vehicle to Grid (ISO 15118) compliance.  I've r

21
Sustainable Design Director
Boulder Associates Architects
LEEDuser Premium Member
20 thumbs up
Wed Jan 29, 2020, 8:36 pm

NC-v4.1 LTc8: Electric Vehicles

NC-v4.1 LTc8:Electric Vehicles
posted by  Brian Johnson  on 

Hello, I have a question regarding the LTc8 Electric Vehicles credit.  If our project only requires 2 parking spaces to have ESVE installed, does that mean each parking space must have an inde

1
Wed Jan 15, 2020, 1:13 pm

Are Electric bikes taken into account in LEED?

NC-v4.1 LTc8:Electric Vehicles
posted by  Maria sAra Di maggio  on 

Hi! Are electric bicycles considered electric vehicles? So is the LEED credit NC-v4.1 LTc8 - Electric Vehicles applicable to Bikes?

0