Combination option?
NC-v4.1 LTc8:Electric Vehiclesposted by Joseph Snider on
Has anybody seen an option to install some EVs and then some EV ready to combine Option 1 and 2? In 2009, there was a way to run weighted calcualtions. We have a project doing a little
“Connected Functionality Criteria for ENERGY STAR” for EVSE
NC-v4.1 LTc8:Electric Vehiclesposted by JONGYEON WON on
Hello all,
I’d like to confirm the exact requirements for this credit.
EV Vehicle Signage and ability to combine with Handicap Parking
NC-v4.1 LTc8:Electric Vehiclesposted by Summer Gorder on
We have a County project that would like to combine EV with Handicap parking. Can that contribute toward the 5%?
Number of spaces
NC-v4.1 LTc8:Electric Vehiclesposted by Norman Sutton on
I have a site with 124 parking spaces. For Option 1 the math points to needing 6.2 spaces (.05 x 124). To earn the credit, will chagring stations for 6 spaces be enough, or will 7
Connected Functionality Criteria
NC-v4.1 LTc8:Electric Vehiclesposted by Rebecca Hatchadorian on
Can anyone give me a better understanding of the "Connected Functionality Criteria" requirement?
EV space accessibility
NC-v4.1 LTc8:Electric Vehiclesposted by Lawrence Rennell on
Do all EV spaces required to be available to the general public?
Off-street parking provided is less than minimum required spaces for EV-ready.
NC-v4.1 LTc8:Electric Vehiclesposted by Erica Downs on
Our project only has 5 parking spaces (all off street), and these are for employees only (FTE = 6), including one HC space.
EV Charger has demand response capability but is not Energy Star
NC-v4.1 LTc8:Electric Vehiclesposted by Jeff Ross-Bain, PE, LEED Fellow, WELL AP on
Hi All,
EVSE and ADA parking spaces
NC-v4.1 LTc8:Electric Vehiclesposted by Bryna Dunn on
Has anyone submitted a project that includes ADA spaces in the spaces served by EVSE? For example, if a total of 3 charging stations are required on a project, and one of those is placed at a
Preferred Parking for Electric Vehicles
NC-v4.1 LTc8:Electric Vehiclesposted by Catherine Blakemore on
Do the electric vehicle parking spaces need to be located within a certain distance of the building entrance? If yes, what is maximum allowable distance and is this distance a radial distance
Electric Vehicles Option 1 requirements
NC-v4.1 LTc8:Electric Vehiclesposted by Olivera Nikolic on
Could you please advise if the below interpretation of LTc8 credit/ Option 1 is correct:
Are all project parking spaces to be included in the count for an Addition, or just the new spaces designed for the Addition?
NC-v4.1 LTc8:Electric Vehiclesposted by Mollie O'Rourke on
We have a project with a 4-story horizontal addition being added (it is actually a healthcare facility, but there are not currently any Q/A's in the HC Forum). Being helathcare, there is a la
Project with no parking
NC-v4.1 LTc8:Electric Vehiclesposted by Summer Gorder on
Can you still earn this credit with a project with no parking?
electric vehicles and reduced parking footprint?
NC-v4.1 LTc8:Electric Vehiclesposted by Craig Flandermeyer on
Is there a way in v4.1 to use these two credits in tandem? V4 has some guidance that increases percentages if both are used. Curious if anyone has attempted both.
Electric Vehicle -required project documentation
NC-v4.1 LTc8:Electric Vehiclesposted by Michelle DeLora on
I have a client asking me about Option 2 - which is ESVE ready for 10% of parking. In the online summary of the credit it does not go into the required uploads.
Signage for EV spaces
NC-v4.1 LTc8:Electric Vehiclesposted by Amanda Polematidis on
For those of you who completed the credit, would one sign for an area with EV charging stations suffice, or does each charging station need a sign?
Option 1: 2% or 5%, Option 2: 6% or 10%?
NC-v4.1 LTc8:Electric Vehiclesposted by Timothy Ian Middleton on
Thanks to LEED User I just discovered the latest version of NC4.1_LTc8 requires 5% of spaces to comply with Electric Vehicle Charging Requirements, instead of 2%.
Level 1 EV chargers - any credit for extensive installations vs a few Level 2's?
NC-v4.1 LTc8:Electric Vehiclesposted by Pooja Sannamani on
Does anyone have any experience in getting credit for more Level 1 chargers? Increasing having clients question whether Level 2 is the right approach for mass rollout due to electrical infras
Existing EV Chargers Serving Project
NC-v4.1 LTc8:Electric Vehiclesposted by Kelli Kimura on
Hi all,
EV spaces for residential portion?
NC-v4.1 LTc8:Electric Vehiclesposted by MARLOES REININK on
We have a mixed-use project (office, hotel, & residential apartments). With this credit now specific to EV spaces only, how are the residential occupant spaces addressed?
EV charging for spillover parking
NC-v4.1 LTc8:Electric Vehiclesposted by Deborah Lucking on
Our project has allocated areas for spillover parking (used a few times a year) in ones and twos around the site, accessible from an alley. much like on-street parking.
EV parking space distribution
NC-v4.1 LTc8:Electric Vehiclesposted by Nadia Bini on
Our project has both employee parking and visitor parking.
EV Ready - Raceway
NC-v4.1 LTc8:Electric Vehiclesposted by Jill Kurtz on
We have a project that is seeking certification. It shares parking with existing buildings on its campus.
On-site EV required if only off-site parking provided?
NC-v4.1 LTc8:Electric Vehiclesposted by Rebecca Aarons-Sydnor on
The first line of the credit states the criteria as "Provide charging infrastructure for electric vehicles for on-site parking." However, under Option 1, it refers to "all parking spaces used by pr
v4.1 Interpretation - Are spaces required to be "preferred"?
NC-v4.1 LTc8:Electric Vehiclesposted by Brian Salazar on
Hello! I asked this question under v4.1 Schools, but this side of the world seems better traveled.
"in close proximity"
NC-v4.1 LTc8:Electric Vehiclesposted by emily reese moody on
Anyone have any guesses as to what the acceptable proximity is to meet this portion of the requirements?
changes within v4.1 requirements
NC-v4.1 LTc8:Electric Vehiclesposted by emily reese moody on
Hi all,
Infrastructure vs EVSE Install, can we get points for both for a total of 2 points?
NC-v4.1 LTc8:Electric Vehiclesposted by Derick Farfan on
Still learning...the way the credit is written it makes it appear that it is you go EITHER go for the Infrastructure Credit (6% or 6 spaces, whichever is greater) OR EVSE Install (2% or 2, whicheve
Exemplary Performance for Electric Vehicles
NC-v4.1 LTc8:Electric Vehiclesposted by Michelle Lambert on
Is Exemplary Performance available for installing more electric vehicle charging stations than the required 2% in v4.1?
EVSE - ISO 15118 compliance
NC-v4.1 LTc8:Electric Vehiclesposted by Mike Cavanaugh on
I'm looking into substituting this credit and pursuing option 1 (2% of spaces) but have a question about the third criteria for EVSE - Vehicle to Grid (ISO 15118) compliance. I've r
NC-v4.1 LTc8: Electric Vehicles
NC-v4.1 LTc8:Electric Vehiclesposted by Brian Johnson on
Hello, I have a question regarding the LTc8 Electric Vehicles credit. If our project only requires 2 parking spaces to have ESVE installed, does that mean each parking space must have an inde
Are Electric bikes taken into account in LEED?
NC-v4.1 LTc8:Electric Vehiclesposted by Maria sAra Di maggio on
Hi! Are electric bicycles considered electric vehicles? So is the LEED credit NC-v4.1 LTc8 - Electric Vehicles applicable to Bikes?