Sample testing required?
Pilot-Credits INpc137:Cleaning and Disinfecting Your Space for Emerging Pathogensposted by on
Hello everyone,
Rainwater management for large industrial site
NC-v4 SSc4:Rainwater managementposted by Erin Holdenried on
Hello - We have a large industrial site that is using a pond to manage about 25% of the rainwater and a vegetated channel to manage about 75% of the rainwater. I believe the vegetated channel
Composting Infrastructure for Mixed-Use Commercial Buildings
Pilot-Credits SSpc129:Comprehensive Compostingposted by Harry James on
Hello everyone,
Trees sf calculation for Protect or Restore Habitat v4.1
NC-v4.1 SSc2:Protect or Restore Habitatposted by Maya Facciolo on
How do we calculate the square footage for contiguous trees for Protect or Restore Habitat v4.1?
Above ground storage tanks
NC-v4 LTc3:High priority siteposted by Samuel Calhoun on
A project I am working on had (QTY: 27) above ground storage tanks removed from the site. This work was overseen by a 3rd party consultant, permitted by the local AHJ, and registered with the DEP.
LEED v5 Pilot Credits
EBOM-v5 PRc1:Project Prioritiesposted by Srecko Curkovic on
Does anyone have more information on pilot credit registration requirements for LEED v5? Thank you!
Documentation for Inherently non-emitting materials
NC-v4 EQc2:Low-emitting materialsposted by Edgar Arevalo on
We have an insulation material that can comply either as inherently non-emitting or meets general emissions evaluation, and has been checked as inherently non-emitting by the contractor,
Counting Dimmable Luminaires
CS-v4 SSc6:Light pollution reductionposted by Helen Biersack on
for a project in lighting zone 3 (U3 allowance or 500 UL and 500 HL for total of 1000), I am reviewing a submittal for a light with the following performance data:
Design for Indoor Air Quality and Infection Control Documentation
Pilot-Credits INpc155:Design for Indoor Air Quality and Infection Controlposted by Katherine Tich on
Anyone with experience documenting this credit - did you submit with the design credits or with the construction credits?
50% of Receptable Controls to meet the Prerequisite
NC-v4 EAp2:Minimum energy performanceposted by Kritika Kharbanda on
We are working on a project where it was missed during equipment procurement that open office furniture is required to have 50% of the receptacles controlled to meet the prerequisite under 90.1-201