Can we certify only the administrative building in a pharmaceutical factory project?

NC-v4 MPR2:Must use reasonable LEED boundaries
posted by  Amgad Khattab  on 

We have a pharmaceutical factory project consists of the following buildings: -
1. An administrative building (Ground + 3). 
2. A Production building (Ground +2).

1
Fri Jun 25, 2021, 1:58 am

Electric Boilers

Sustainable MEP Leaders
posted by  Sarah Gudeman  on 

Anyone have experience with electric boilers?

10
Principal | Practice Lead
BranchPattern
LEEDuser Premium Member
6 thumbs up
Mon Jun 21, 2021, 7:29 pm

Group Project Scoring

EBOM-v4 EAc7:Renewable energy and carbon offsets
posted by  Andy Rhoades  on 

How do I score EAc7 when certifying for a group project? I have the VER proposals for the three buildings but don't know how to score them together. Thanks!

 

0

Remediation of LEED Project Area or only disturbed areas

NC-v4 LTc3:High priority site
posted by  Mark Meaders  on 

We have a project that has had a Phase 1 and II ESA performed. It found there was acetone and mercury on site.

1
Fri Jun 18, 2021, 2:07 pm

One Product Counting Towards Multiple Credits

NC-v4 MRc2:Building product disclosure and optimization - environmental product declarations
posted by  Summer Gorder  on 

Can one product count towards multiple options and/or credits for more points? How does the bonus credit work if a product has an EPD, and meets LCA requirements for Option 2?

3
Default Avatar
Sustainability Engineer
Ecosolutions
LEEDuser Basic Member
6 thumbs up
Fri Jun 18, 2021, 12:13 pm

reduced parking (from pre-existing site condition) counting as "no parking"

NC-v4.1 LTc7:Reduced Parking Footprint
posted by  Chris Flint Chatto  on 

We have a project, a large addition/reconfiguration on an institutional campus, that is being built above, tying into.

2
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Fri Jun 18, 2021, 12:00 pm
1
Fri Mar 4, 2022, 6:17 pm

EV Charging Stations

NC-v4 LTc8:Green vehicles
posted by  Dianne Herrin  on 

Hello - My client is preparing to purchase Tesla EV charging stations to meet LEED v4 requirements. These stations will work only with Teslas.

3
Senior Principal | Director of Sustainability Integration
SmithGroup
LEEDuser Expert
43 thumbs up
Wed Jun 16, 2021, 4:55 pm

Radiant Temperature

EBOM-v4 EQc3:Thermal comfort
posted by  Craig Wilson  on 

What is the difference between air temperature and radiant temperature?

1
Fri Jul 30, 2021, 3:52 am

Renewable Energy - Confirmation of Renewable Attribute Ownership

CS-v4.1 EAc5:Renewable Energy
posted by  Levi Jimenez  on 

We have a site with a substantial solar array that is owned by the building owner.  The LEED Credit form requires uploaded supporting documentation as follows: "upload confirmation

3