Take back program language for contractCI-v4 MRc2: Interiors life-cycle impact reductionposted by Brightworks Sustainability on Jun 12, 2018, 12:59 pm
Does anyone have a sample contract with a manufacturer for a take back program? My project teams are asking about this and we are not sure who the responsibility falls on - owner?... |
|
Alternative Structure and Enclosure LimitNC-v4 MRc3: Building product disclosure and optimization - sourcing of raw materialsposted by Nuttanee Vongveeranonchai on Jun 13, 2018, 2:35 am
Hi all, I just came across this addenda that allows alternative... |
|
CFR and O&M plan informationCI-v4 EAp1: Fundamental commissioning and verificationposted by Michael on Jun 13, 2018, 4:23 am
Hi LEEDusers, My project is an small office pursing CI-v4 in a Core n Shell... |
|
4VOC certificationCI-v4 EQc2: Low-emitting materialsposted by DAVE LI on Jun 13, 2018, 5:45 am
Japan has a Third Party certification called 4... |
|
AgBB standard test for projects inside the U.S.CI-v4 EQc2: Low-emitting materialsposted by Nativa Architecture on Jun 13, 2018, 12:03 pm
Dear All, If a sealant is tested and certified as compliant to GEV EMICODE EC1+ standard requirements, and is purchased in Europe by an european millworker which will install furniture... |
|
Coordination / separation with BD&C projectND-v2009 GIBp1: Certified green buildingposted by Stacey Olson on Jun 13, 2018, 9:15 pm
I'm working on a project with a very narrow lot line immediately adjacent to the BD&C registered project. In terms of separation of documentation, my understanding is that the BD&C... |
|
Pre Fab Building ComplianceNC-v4 EQc2: Low-emitting materialsposted by Kristen Magnuson on Jun 17, 2018, 2:36 pm
Is it still possible to get 3 points for 5 compliant credit categories, if the building is entirely constructed off-site and then brought to the site and assembled? I believe this strategy still... |
|
Achieving credit in a Rest AreaNC-v4 LTc7: Reduced parking footprintposted by Julie Hardy on Jun 19, 2018, 11:50 am
The provincial government is designing a Rest Area for an important Highway, the project will also is to be operated and owned by the provincial government. There is no local code requirement for... |
|
Number of Parking Spaces Required by Local Code.NC-2009 SSc7.1: Heat island effect - nonroofposted by Adrian Arenas on Jun 19, 2018, 11:54 pm
Hello Everyone, One quick question regarding SSc7.1 For Option 2, to comply with 50% of parking spaces undercover: Does the credit refer to the total number Parking Spaces... |
|
EQc6-lightingNC-v4 EQc6: Interior lightingposted by CR ZHANG on Jun 20, 2018, 2:53 am
strategy A: if cut sheet for cd/m2 cannot be provided, could i use conversion forum: L(lux)/R(reflectance) = E (cd/m2) to get the independent result of the data? How should I consider 45-... |