Topic | Recent |
---|---|
Can New Construction project use requirement of Warehouse and Distribution center to count point?NC-v4 LTc4: Surrounding density and diverse usesposted by Michael on Jan 10, 2023, 6:16 am
Hi LEED expert, my project is a manufacturing plant with a warehouse. The warehouse accounts for 46% of the total GFA. The project will be registered under New Construction. For this credit... |
|
Does LEED require a third-party to verify the LCA report?NC-v4.1 MRc1: Building life-cycle impact reductionposted by Michael on Aug 18, 2022, 5:52 am
My project is using One Click software to do LCA report. I would like to ask if LEED requires an independent professional (from One Click for example) to verify our LCA report before we submit it... Last reply: Sagar Siripuram, Nov 8, 2022, 1:37 am |
|
Is it ok if we choose CO2 Sensors with fixed default setpoints from the manufacturer?NC-v4 EQc1: Enhanced indoor air quality strategiesposted by ed HvacSimulator on Nov 6, 2022, 10:00 pm
Hi, We are following Leed V4 for New Construction. It is difficult to find the CO2 sensors for crowded... |
|
Indoor Water Use Reduction Calculator v4.0NC-v4.1 WEp2: Indoor water use reductionposted by Dung Bui on Sep 4, 2019, 11:05 pm
Hi everyone, I'm currently working on the credit Indoor Water Use Reduction (Calculator 4.0 excel sheet) and have a question concerning fixture's design flow rate. The fixtures used... Last reply: emily reese moody, Oct 17, 2022, 12:50 pm |
|
Problem with Rainfall Event CalculatorNC-v4 SSc4: Rainwater managementposted by Timothy Ian Middleton on Oct 5, 2022, 4:29 am
We have just realised that the percentile value given by the LEED Rainfall Event Calculator (https://www.usgbc.org/... Last reply: Gustavo De las Heras Izquierdo, Oct 5, 2022, 1:03 pm |
|
Green area reserved for future building developmentNC-v4.1 SSc2: Protect or Restore Habitatposted by Michael on Aug 29, 2022, 1:50 pm
My project has 2 phases of development. Currently, we only apply LEED for phase 1. There is a big greenery area, reserved for future building in phase 2. Can we count this greenery area as a... Last reply: Kimiko Marinacci, Sep 21, 2022, 2:52 pm |
|
Standard for the baseline of the cold storage in a factoryNC-v4.1 EAp2: Minimum Energy Performanceposted by Michael on Sep 11, 2022, 1:40 pm
My factory project has cold storage (10oC) and a freezer (-13oC). For the factory, we use ASHRAE 90.1-2016 as normal but for the cold storage and freezer, what is the standard to set up the... Last reply: Marcus Sheffer, Sep 12, 2022, 7:13 pm |
|
Daylight sensors in a factory with skylightNC-v4.1 EAp2: Minimum Energy Performanceposted by Michael on Sep 11, 2022, 1:27 pm
My factory project has skylights on the roof and when I told the MEP engineers that they need to install daylight sensors for daylight area under the skylight, they refused as changing the... Last reply: Marcus Sheffer, Sep 12, 2022, 6:00 pm |
|
Install submeters for a factory with 90% of Process loadNC-v4 EAc3: Advanced Energy Meteringposted by Michael on Aug 31, 2022, 11:44 pm
My project is a factory with more than 90% of energy consumption coming from Process load (for production purposes). HVAC, lighting, pump, and fan all together only account for least than 10% of... Last reply: Marcus Sheffer, Sep 1, 2022, 12:59 pm |
|
Campus approach: can we install water meter for the entire landscape, sanitaryware as a wholeNC-v4 WEc4: Water meteringposted by Michael on Aug 25, 2022, 5:37 am
My project is a campus project, consisting of 4 individual buildings. To fulfill this credit, can I install 1 meter to monitor sanitaryware for 4 buildings together as a whole? or I have to split... Last reply: Maeve Donohue, Aug 25, 2022, 9:21 am |