Lighting Controls in Unoccupied Spaces

EBOM-2009 EAc3.1: Performance measurement - building automation system
posted by Clint Fogg on Apr 5, 2018, 4:21 pm

Good afternoon, I am working on credit EAc3.1 for an...

Last reply: Summer Minchew, May 2, 2018, 8:51 am

BAS

EBOM-2009 EAc3.1: Performance measurement - building automation system
posted by VISHESH AGARWAL on May 17, 2016, 8:24 am

Is it necessary to have exterior lighting monitor and control to achieve this credit point. if interior is on BMS, Will i able to take that credit.

Last reply: Dave Hubka, May 17, 2016, 8:27 am

Tenants

EBOM-2009 EAc3.1: Performance measurement - building automation system
posted by Gustavo De las Heras Izquierdo on Apr 25, 2016, 6:48 pm

Our project is an office tower with 30 tenants. Does the BAS need to control tenant's systems? HVAC is centralized (cooling tower and chillers), but each tenant controls fan& coils within the...

Last reply: Dave Hubka, Apr 26, 2016, 7:48 am

Lighting Controls Exemption

EBOM-2009 EAc3.1: Performance measurement - building automation system
posted by Katherine Roth on Sep 11, 2015, 10:10 am

Our project received the following review comment:
"If any building spaces do not have automatic lighting control, provide information on the use and square footage of these spaces.
...

Last reply: Melissa Kelly, Dec 15, 2015, 3:27 pm

Sensors calibration during the performace period

EBOM-2009 EAc3.1: Performance measurement - building automation system
posted by Agnieszka Rylska on Mar 18, 2015, 10:56 am

Is it necessary to calibrate sensors during the performance period even if the manufacturer’s recommended interval didn't pass yet? Or can it only be mentioned in the maintenence plan that the...

Last reply: Melissa Kelly, Dec 10, 2015, 10:18 am

BAS- whole building

EBOM-2009 EAc3.1: Performance measurement - building automation system
posted by Craig Wilson on Oct 22, 2014, 12:47 pm

If our project's BAS controls 100% of the building's heating and air conditioning, but only 35% of the building's ventilation (by square footage), can we still pursue this credit? (Lighting is...

Last reply: Hannah Bronfman, Dec 11, 2014, 3:28 pm

BAS localized lighting

EBOM-2009 EAc3.1: Performance measurement - building automation system
posted by ethan adams on Apr 2, 2014, 10:15 am

Motion sensors seem to be a natural, low-cost localized lighting control for this credit except for this one line: "Demonstrate that the BAS is being used to inform decisions regarding changes in...

Last reply: ethan adams, Apr 2, 2014, 11:07 am

Humidity

EBOM-2009 EAc3.1: Performance measurement - building automation system
posted by Gustavo De las Heras Izquierdo on Mar 6, 2014, 8:21 pm

I was wondering if there is a minimum set of comfort parameters which HAVE TO be measured by the BAS.

I am particularly interested in knowing if the Building Automation System HAS to...

Last reply: Dave Hubka, Mar 7, 2014, 9:39 am

sample BAS docs

EBOM-2009 EAc3.1: Performance measurement - building automation system
posted by Tristan Roberts on Jan 17, 2014, 12:06 pm

Thanks to David Hubka, LEEDuser has added two sample documents to our Toolkit for this credit—a BAS summary report, and a preventive maintenance checklist. These documents were used sucessfully...

Sensor Calibration Requirement

EBOM-2009 EAc3.1: Performance measurement - building automation system
posted by Christopher Pinkowski on Feb 23, 2012, 10:12 am

Does anyone have experience complying with this requirement? The reference guide does not offer many details on how this aught to be achieved. Can it be done in-house? Would most mechanical/TAB...