Lighting Zone for a Terminal Building

NC-v4 SSc6: Light Pollution Reduction
posted by Gustavo De las Heras Izquierdo on Mar 15, 2023, 8:46 pm

Hello,

We are certifying the Terminal Building in a new international airport. We wonder how to categorize the project, since lighting zones are not well defined. A Terminal Building needs...

Last reply: Afogreen Build, Mar 7, 2024, 3:33 am

100% nonportable water for cooling tower

NC-v4 WEc3: Cooling tower water use
posted by Thomas Tran on Feb 13, 2019, 4:08 am

Hi,

LEED reference document says in the Required document Table (page 309):

- Nonportable water analysis (if use 100% nonportable water) -------------------------------------- 2...

Last reply: Afogreen Build, Mar 7, 2024, 3:24 am

Partial Floor LEED Certification

CI-v4 MPR3: Must comply with project size requirements
posted by Edgar Arevalo on Mar 7, 2024, 12:14 am

I have a project that is a partial floor fit-out where the client would like that partial space to be LEED certified.  The project space is approximately 52% - 60% of the total floor area, but it...

Office space only going for partial renovation.

CI-v4 MPR2: Must use reasonable LEED boundaries
posted by shashank gangil on May 14, 2021, 8:30 am

We have a client who lease out three floors in a office building in Hong Kong. They are currently renovating a part of these three floors. Total renovated area is approximately 30% of the total...

Last reply: Edgar Arevalo, Mar 7, 2024, 12:14 am

Existing PV on previously certified project

NC-v4 EAc5: Renewable energy production
posted by Yu Zhang on Feb 13, 2019, 3:33 pm

I have a project that is a new building located on a previous certified LEED project with PV production.  The previous project had >90% offset by energy use and >100% offset by cost from...

Last reply: Marcus Sheffer, Mar 6, 2024, 12:20 pm

Location Valuation Factor

NC-v4 MRc3: Building product disclosure and optimization - sourcing of raw materials
posted by Shannon Oletic on Jul 15, 2019, 6:01 pm

Hello, 

Do all components of a product have to comply with the 160km sourcing requirements in order to apply the location valuation factor in v4? For example, if the recycled scrap within...

Last reply: Dave Hubka, Mar 6, 2024, 9:34 am

LEED Communities- non-contiguous land included

ND-v4 MPR2: Must use reasonable LEED boundaries
posted by Lidia Johansen on Mar 5, 2024, 6:21 pm

Lidia, you're correct there's no LEEDuser forum for Communities despite its official status. I'm unaware of non-contiguous land provisions in Communities, but it may not be a good idea to look toward ND because the two systems were developed very differently. ND doesn't allow non-contiguous land, except for intervening street rights-of-way. For Communities, you may want to check with USGBC staff. Eliot Log in or register to post comments 1 Vote up! Thank you for your response Eliot Log in or register to post comments 0 Vote up! ...

Last reply: Lidia Johansen, Mar 6, 2024, 4:21 am

50% surface area reuse

CI-v4.1 MRc2: Interiors life-cycle impact reduction
posted by Mark Ragucci on Jan 15, 2020, 9:40 am

how is this credit calculated? can in include existing floor slab and deck? we are leaving a portion of the exiting walls that are about 20ft tall and our ceilings will be at 9'. can i calculate...

Last reply: Stephani Carter, Mar 5, 2024, 7:34 pm

Backup Documentation

NC-v4 WEc4: Water metering
posted by Michelle Rosenberger on Mar 5, 2024, 11:09 am

on this forum with respect to 'what to upload onto LO platform?'. good post! Log in or register to post comments 0 Vote up! HI all- this is one of several credits that may not cite prescriptive...

Last reply: Karen Joslin, Mar 5, 2024, 12:27 pm

Building will be used by the client, not be leased to 3rd party. need of "tenant design & construction guidelines document"?

CS-2009 SSc9: Tenant Design and Construction Guidelines
posted by prudhvi mahadev on Feb 7, 2018, 1:03 am

hello,

im pursuing a project which is going with the rating LEED 2009 C&S. i have a question, in my case the owner himself will use the space for his own purpose and will not be leased...

Last reply: , Mar 5, 2024, 7:24 am