Street Light BUG Rating

NC-v4 SSc6: Light Pollution Reduction
posted by Danielle Waters on Feb 13, 2023, 2:22 pm

If Street Lights on the public sidewalk adjacent to public streets are within project scope and LEED Boundary, are they required to comply with BUG Rating? What if fixtures are required by city...

Last reply: Danielle Waters, Feb 14, 2023, 4:15 pm

Hydrozones

NC-v4 WEp1: Outdoor water use reduction
posted by Charles Hall on Feb 13, 2018, 5:11 pm

I am a little unsure about how to generate hydrozone areas. For instance, with a...

Last reply: Julio Fernandez Amodia, Feb 14, 2023, 11:02 am

Biophilic design plan

Pilot-Credits EQpc123: Designing with Nature, Biophilic Design for the Indoor Environment
posted by Priscillia Champagne on Jun 2, 2022, 8:16 am

I understand that the final result must be that the project implements five distinct design strategies. What is more difficult to grasp is how the "Design with nature documentation template"...

Last reply: Adriana Hansen, Feb 13, 2023, 4:44 pm

Modeling District Energy via Option 1 path2 full DES

NC-v4 EAc2: Optimize Energy Performance
posted by elvin ruya on Feb 13, 2023, 3:36 pm

Hi, 

For a campus project, we would like to go with option 1 path2 full...

Waling Distance 400 m or 800 m?

CS-v4 LTc5: Access to quality transit
posted by Stephan Zweig on Feb 10, 2023, 3:26 am

Dear all,

1) Does subway station as...

Last reply: Konstantina Kalliakoudi, Feb 13, 2023, 10:58 am

How to get points on Material Ingerident

NC-v4.1 MRc2: Environmental Product Declarations
posted by Nagaraj Sankar on Feb 13, 2023, 2:40 am

Hi User ,

One of our project ,20 permanently installed materials are purchased under the EPD credit on one of our projects.

we can reach 2 points on that credit, but the client...

Last reply: Gustavo De las Heras Izquierdo, Feb 13, 2023, 10:25 am

Regarding Energy Simulation

Data-Centers-NC-v4 EAp2: Minimum Energy Performance
posted by Nagaraj Sankar on Feb 8, 2023, 6:25 am

One of our data center projects has an electrical room. This electrical room didn't have regular occupants.  In this case, do we need to provide fresh air for that space? 

In Ashrae 62.1 (...

Last reply: Tyler Thumma, Feb 13, 2023, 7:48 am

Lighting Mandatory Provision in Tenant space

CS-v4 EAp2: Minimum Energy Performance
posted by Teerawat W. on Feb 6, 2023, 4:58 am

Our project is a core and shell office. The owners are provided with complete lighting fixtures in the tenant space (shell).

1. Does this space need to comply with all requirements under...

Last reply: Tyler Thumma, Feb 13, 2023, 7:45 am

Regarding Energy Simulation

Data-Centers-NC-v4 EQp1: Minimum indoor air quality performance
posted by Nagaraj Sankar on Feb 8, 2023, 6:31 am

One of our data center projects has an electrical room. This electrical room didn't have regular occupants.  In this case, do we need to provide fresh air for that space? 

In Ashrae 62.1 (...

Last reply: Dave Hubka, Feb 12, 2023, 9:02 am

Question about calculating the % of Improvement in Energy Performance- Projec with PV arrays

NC-v4 EAc2: Optimize Energy Performance
posted by Stephan Zweig on Feb 10, 2023, 5:03 am

Dear LeedUsers,

In our  project we have PV arrays which produce electricity and provide this electricity to the Network.

1) Can this electricity production  after it converted in...

Last reply: Stephan Zweig, Feb 12, 2023, 1:21 am