Log in
Forum
Topic

LEED AP + Independent CxA

NC-v4 EAc1: Enhanced Commissioning
posted by Mike D on Mar 26, 2015, 6:07 am

If a team is appointed as LEED AP on a project, can they also act as the independent...

Last reply: Marcus Sheffer, Jun 15, 2018, 12:56 pm

Zero lot line projects

NC-v4 SSc4: Rainwater management
posted by Gustavo De las Heras Izquierdo on Mar 26, 2015, 12:47 pm

Path 3 states: "manage on site the runoff from the developed site for the 85th percentile ". I guess this requirement was made to exclude the sidewalk from calculations. Am I reading this...

Last reply: Dave Hubka, May 16, 2022, 2:10 pm

VOC content requirements for adhesives and sealants

NC-v4 EQc2: Low-emitting materials
posted by Craig Graber on May 13, 2015, 7:22 pm

If I read the v4...

Last reply: Wai Hoong Yap, Sep 23, 2021, 9:04 pm

Recycled Content for differnet plants from the same manufacturer

NC-2009 MRc4: Recycled Content
posted by Elena Enache-Pommer on Jan 15, 2015, 3:58 pm

Hypothetically, if Plant 1 has 15% pre-consumer recycle, Plant 2 has 25% and Plant 3 has 35%. Can an average be used of 25% to meet the credit since it is challenging to track where specifically...

Last reply: Keith Lindemulder, Jun 13, 2018, 4:39 pm

Naturally ventilated elevator lobby in mech. ventilated bldg.

NC-2009 IEQc2: Increased Ventilation
posted by Lawrence Lile on Jan 19, 2015, 3:30 pm

I have a very small elevator lobby, which has a little mini-split unit without outside air. It is the main entrance for an apartment building, and every time it is occupied, there will be an...

Last reply: Jean Marais, Jan 20, 2015, 2:04 pm

Are Door Distributors Required to be FSC Certified?

NC-2009 MRc7: Certified Wood
posted by Marcia Weekes on Feb 9, 2015, 3:36 pm

I provide consulting to many General Contractors working on buildings pursuing LEED Certification. Unfortunately, the...

Last reply: Judy Landwehr, Feb 10, 2015, 4:50 pm

Measurement & Verification and PI Form 1

NC-2009 EAc5: Measurement and Verification
posted by Ivan Romero on Jun 15, 2015, 7:25 pm

I'm still not completely clear on the reporting commitment for energy and water usage data. The responses to prior questions about this subject indicate a reporting commitment of 5 years if...

Last reply: Debra a. Lombard, Aug 9, 2016, 11:10 am

Case 1, Option 2 baseline

EBOM-2009 WEc3: Water Efficient Landscaping
posted by Ryan Tinus on Jun 17, 2015, 1:42 pm

Hi,
I am attempting to calculate the baseline for irrigation, and came across an EPA Watersense Water Budget tool that can be used to determine the water efficiency of landscaping. For...

Last reply: William Weaver, Jan 16, 2018, 4:56 pm

Documenting Master Site Credits

LEED Guidance for Campuses and Multiple Buildings
posted by Deborah Lucking on Jul 10, 2015, 5:57 pm

I got this below from the LEED Help Center, which I find really confusing, and does not accord with the current LEED Online for Campus/Master Site format. Does anyone have any insight?

...

Last reply: Michelle Rosenberger, Apr 12, 2019, 12:24 pm

Rating System Selection CI

LEED Rating System Selection
posted by Christian Bösselmann on Aug 13, 2015, 10:52 am

Dear all
I am hesitating whether the following project could obtain a CI certificate for the entire building:
-existing office building
-one entity owns the entire building...

Last reply: Nadav Malin, Aug 14, 2015, 8:36 am