Option 3 Guidance Now Available!NC-v4 MRc4: Building product disclosure and optimization - material ingredientsposted by Paula Melton on Nov 14, 2015, 3:52 pm
The actual points won't be achievable for a few months, but USGBC has released implmentation guidance. Please see the details here: |
|
SSc3 and MRc2Schools-2009 SSc3: Brownfield Redevelopmentposted by Robert Fiala on Nov 17, 2015, 7:01 am
We have a school project registered under LEED for Schools 2009. The project involves the demolition and asbestos abatement of the existing school building then the construction of a new school... |
|
Circulation space around the building coreCS-v4 EQc4: Daylightposted by Julien Richard on Nov 25, 2015, 4:52 am
For Core&Shell projects, the reference guide specifies : “Assume that the entire floor plate, except for the core, will be regularly occupied space “. |
|
LEED Online Form Help for Process WaterRetail-CI-v2009 WEp1: Water Use Reductionposted by Sara Zoumbaris on Nov 25, 2015, 4:32 pm
Hello, I have a project with three pieces of process water equipment and I have a few questions about the form. 1. Does the "cycles/ day" column represent an estimated cycles per day this... |
|
The three dimensional orientation of the luminairePilot-Credits SSpc7: Light Pollution Reductionposted by Aly Rawji on Nov 29, 2015, 2:06 am
Can you please provide a sample for this, what is required for "The three dimensional orientation of the luminaire (plan/ elevation)"? Does this mean I need to provide the site lighting layout in... |
|
Tenant Neutral OptionCS-2009 WEc2: Innovative Wastewater Technologiesposted by Miriam Ramirez Baumgarten on Dec 9, 2015, 10:12 am
Hi, Our project is following the Tenant Neutral option for WEp1c3 because even though the developer is providing all plumbing fixtures, preparations are available in case the upper floors... |
|
Duct Seal levelNC-2009 IEQc4.1: Low-emitting materials - adhesives and sealantsposted by Sarfaraj Khan on Dec 10, 2015, 10:48 am
Minimum duct seal level must comply with table 6.4.4.2A- Ashrae 90, i have this in my specification for duct and i think it apply only to G.I Duct, Not to pre insulated duct, please anyone can... |
|
LCA Part B – Use stage of 60 yearsNC-v4 MRc1: Building life-cycle impact reductionposted by Petr Vogel on Dec 11, 2015, 10:10 am
Since B stage is compulsory to be included I would like to ask similarly how deep should we dig in. Having in mind the following: |
|
LCA Part C – End of LifeNC-v4 MRc1: Building life-cycle impact reductionposted by Petr Vogel on Dec 11, 2015, 10:09 am
The credit says cradle to grave so it is obvious that this part has to be included. Is there any guidance how should it be included? Having in mind two methods: The most simple method:... |
|
Line of sight at intersectionsPilot-Credits PC14: Walkable Streetsposted by Katie Peterschmidt on Dec 11, 2015, 2:51 pm
Hello - has anyone had an issue with Requirement #9: where should the 50' tree spacing start from a busy intersection? We have an urban building with 3 facades, and the required vehicular line... |