Heat Island Mitigation with Cool Walls

CS-v4.1 INc1: Innovation
posted by Carlos De Leon on Aug 13, 2024, 6:30 pm

Hello LEED community!

I'm currently working on a project aimed at earning the Innovation Pilot Credit for Heat Island Mitigation using Cool Walls, and we’re using Sherwin Williams paints....

IPpc90 Social Equity within the Project Team

Pilot-Credits IPpc90: Social equity within the operations and maintenance staff
posted by Alison Kerr on Aug 13, 2024, 2:37 pm

IPpc90 in LEED Online, v4, BD+C, NCMR is "Social equity within the project team." Not "...the operations and maintenance staff." My comment is regarding the Project Team Pilot credit. 

...

Rainwater Management- No discharge at all or No immediate discharge?

NC-v4 SSc4: Rainwater management
posted by Junru Shen on Aug 8, 2018, 2:34 pm

Hi All, 

We are pursuing option 1 of the Rainwater management credit on our LEED v4 new construction project. I find that the credit requirement is not super clear on whether controlled...

Last reply: Catarina Costa Goncalves, Aug 13, 2024, 4:47 am

Documentation needed for a renovation project

NC-v4 EAc3: Advanced Energy Metering
posted by Audrey LEDESERT on Nov 10, 2023, 2:49 am

Hi,

I'm working on a renovation project, in Core & Shell. Concerning the different meters, some of them are existing meters.

How do we have to consider those existing meters ?...

Last reply: Afogreen Build, Aug 13, 2024, 2:59 am

REACH Regulation

NC-v4.1 EQc2: Low-emitting materials
posted by Monika Fabiánová on Aug 12, 2024, 10:36 am

Hello. 

Our project is in the EU- is it sufficient for this credit only to have confirmation that some materials do not contain any volatile organic compounds (VOCs) according to...

TUV PROFiCERT acceptable for VOC emission?

NC-v4.1 EQc2: Low-emitting materials
posted by sompoche sirichote on Jun 13, 2023, 5:08 am

Hi, 

Could anyone help confirm if LEED consider products with TUV PROFiCERT-product Interior / Interior PREMIUM mark meeting v4.1...

Last reply: Harry James201, Aug 12, 2024, 6:17 am

Quality views

LEED v4.1 Discussion Forum
posted by ROMANE RICOU on Aug 9, 2024, 8:32 am

Hello,

I'm doing a certification for a LEED v4 BD+C: NC project. For the Quality views credit I'd like to know if we have to fill in the excel? If so, do we have to fill in the information...

Last reply: Celeste Londyn, Aug 12, 2024, 3:17 am

I-Tree Planting Calculator- lifetime of project

Pilot-Credits SSpc158: Onsite Carbon Sequestration Through Plantings
posted by Nicolette Francis on Feb 25, 2022, 3:34 pm

Hi ,

Can someone advise me on what value to input for 'Years of the Project' within the i-Tree Planting tool. Should I use 60 years based on the LCA credit for LEED v4 or can I base this...

Last reply: Rachael Johnson, Aug 9, 2024, 3:45 pm

Monitoring during LEED Review stage?

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Marine Petrosyan on Aug 8, 2024, 11:38 am

Hi, All!

We have selected the Combined review process. I would appreciate it if you could advise, whether during the review stage the monitoring at the project site is mandatory by the...

Last reply: Marine Petrosyan, Aug 9, 2024, 10:17 am

Option 1 Lighting Control- Undeveloped Future Tenant Spaces

NC-v4 EQc6: Interior lighting
posted by James Keohane on May 25, 2018, 5:13 pm

I am working on a project that has the majority of individual occupant spaces that will be completely finished with lighting controls meeting the requirements for Option 1.  However, we also have...