Topic | Recent |
---|---|
Recertification of part of building and certifying a part under BD+CEBOM-v4 MPR2: Must use reasonable LEED boundariesposted by Azra on Nov 13, 2023, 10:15 am
Hi, |
|
% of Male Occupants using restrooms with urinals when project also includes All-gender restroomsCI-v4 WEc1: Indoor water use reductionposted by Yarden Harari on Nov 10, 2023, 2:31 pm
Hi - we've received a comment on our water use calculations about changing the % of male occupants using restrooms with urinals because the project also includes several single occupant all-... Last reply: Yarden Harari, Nov 13, 2023, 10:01 am |
|
Existing building and extension building in one certificationNC-v4 MPR2: Must use reasonable LEED boundariesposted by Helena Garcia on Nov 13, 2023, 5:35 am
In our team we are conducting a study for the construction of an extension of an existing building. Last reply: Dave Hubka, Nov 13, 2023, 9:09 am |
|
ROhS DirectiveHealthcare-v2009 MRc4.2: PBT source reduction - lead, cadmium and copperposted by Gustavo De las Heras Izquierdo on Feb 27, 2014, 8:32 pm
Is the ROhS Directive a valid approach for demonstrating the cable meets the credit requirements? Please check this out: http://www.... Last reply: Aury Hathout, Nov 11, 2023, 9:01 pm |
|
Equations and calc methodsEBOM-v4.1 EAp3: Energy Performanceposted by Ricardo Filho on Feb 21, 2023, 5:01 am
I am doing some research on LEED v4.1 O+M and I have a number of questions. Last reply: Saba Hajizadeh, Nov 10, 2023, 4:29 pm |
|
Flush-out areaNC-v4.1 EQc4: Indoor air quality assessmentposted by Charalampos Giannikopoulos on Nov 9, 2023, 4:27 pm
Could you kindly confirm than only the net (excluding wall surfaces, shafts, etc.) and not gross area of a building needs to be considered for flush-out? Last reply: Dave Hubka, Nov 10, 2023, 12:24 pm |
|
LEED AP HomesMid-Rise-v4 INc2: LEED Accredited Professionalposted by Laura Rojas on Nov 10, 2023, 10:13 am
AI am working on a Residential BD+C |
|
Parksmart- Parking Detection for a Mixed ProjectParksmart Discussion Forumposted by Alokmay Behera on Nov 9, 2023, 12:55 am
Greetings. I am working on a mixed project targeting Parksmart for the parking area. In the design stage, the credits B3 and B4- Way Finding Systems- External and Internal were targeted.... Last reply: Paul Wessel, Nov 10, 2023, 9:44 am |
|
Two separate buildings / 2 waste haulers / 1 reportNC-v4 MRp2: Construction and demolition waste management planningposted by Allison Para on Nov 1, 2023, 3:04 pm
Hello Users, I have a question regarding 2 separate (identical) residential buildings, registered to LEED separately by architect (NCv4bdc), located a court yard across from one another,... Last reply: Allison Para, Nov 9, 2023, 4:25 pm |
|
Views creditCI-v4.1 EQc8: Quality Viewsposted by Denise Bates on Sep 13, 2022, 12:05 pm
in a CI project where you do not have access to the building's VLT, is there a default value we can use? not finding guidance on it Last reply: Nadia Azzam, Nov 9, 2023, 11:39 am |