IPpc90 Social Equity within the Project Team

Pilot-Credits IPpc90: Social equity within the operations and maintenance staff
posted by Alison Kerr on Aug 13, 2024, 2:37 pm

IPpc90 in LEED Online, v4, BD+C, NCMR is "Social equity within the project team." Not "...the operations and maintenance staff." My comment is regarding the Project Team Pilot credit. 

...

Rainwater Management- No discharge at all or No immediate discharge?

NC-v4 SSc4: Rainwater management
posted by Junru Shen on Aug 8, 2018, 2:34 pm

Hi All, 

We are pursuing option 1 of the Rainwater management credit on our LEED v4 new construction project. I find that the credit requirement is not super clear on whether controlled...

Last reply: Catarina Costa Goncalves, Aug 13, 2024, 4:47 am

Documentation needed for a renovation project

NC-v4 EAc3: Advanced Energy Metering
posted by Audrey LEDESERT on Nov 10, 2023, 2:49 am

Hi,

I'm working on a renovation project, in Core & Shell. Concerning the different meters, some of them are existing meters.

How do we have to consider those existing meters ?...

Last reply: Afogreen Build, Aug 13, 2024, 2:59 am

REACH Regulation

NC-v4.1 EQc2: Low-emitting materials
posted by Monika Fabiánová on Aug 12, 2024, 10:36 am

Hello. 

Our project is in the EU- is it sufficient for this credit only to have confirmation that some materials do not contain any volatile organic compounds (VOCs) according to...

TUV PROFiCERT acceptable for VOC emission?

NC-v4.1 EQc2: Low-emitting materials
posted by sompoche sirichote on Jun 13, 2023, 5:08 am

Hi, 

Could anyone help confirm if LEED consider products with TUV PROFiCERT-product Interior / Interior PREMIUM mark meeting v4.1...

Last reply: Harry James201, Aug 12, 2024, 6:17 am

Quality views

LEED v4.1 Discussion Forum
posted by ROMANE RICOU on Aug 9, 2024, 8:32 am

Hello,

I'm doing a certification for a LEED v4 BD+C: NC project. For the Quality views credit I'd like to know if we have to fill in the excel? If so, do we have to fill in the information...

Last reply: Celeste Londyn, Aug 12, 2024, 3:17 am

I-Tree Planting Calculator- lifetime of project

Pilot-Credits SSpc158: Onsite Carbon Sequestration Through Plantings
posted by Nicolette Francis on Feb 25, 2022, 3:34 pm

Hi ,

Can someone advise me on what value to input for 'Years of the Project' within the i-Tree Planting tool. Should I use 60 years based on the LCA credit for LEED v4 or can I base this...

Last reply: Rachael Johnson, Aug 9, 2024, 3:45 pm

Monitoring during LEED Review stage?

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Marine Petrosyan on Aug 8, 2024, 11:38 am

Hi, All!

We have selected the Combined review process. I would appreciate it if you could advise, whether during the review stage the monitoring at the project site is mandatory by the...

Last reply: Marine Petrosyan, Aug 9, 2024, 10:17 am

Option 1 Lighting Control- Undeveloped Future Tenant Spaces

NC-v4 EQc6: Interior lighting
posted by James Keohane on May 25, 2018, 5:13 pm

I am working on a project that has the majority of individual occupant spaces that will be completely finished with lighting controls meeting the requirements for Option 1.  However, we also have...

Last reply: Joyce Kelly, Aug 9, 2024, 9:13 am

Soil tests requirements

CS-v4.1 SSc2: Protect or Restore Habitat
posted by Katrin Niedermeier on Apr 12, 2023, 7:27 am

Andrea Vickers LEEDuser Basic Member 1 thumbs up August 9, 2024- 8:51 am Hi Katrin, did you ever sort out what was required? I can add that we have submitted without soil tests and the preliminary comments asked us to include soil tests, but I'm curious what others' experiences have been given the contradiction in the reference guide. Thanks *edit* this is answered in another thread!:  https://leeduser.buildinggreen.com/forum/soil-tests-no-longer-required Log in or register to post comments ...

Last reply: Andrea Vickers, Aug 9, 2024, 8:51 am