How to calculate EFLH in a Minimum calcuratorRetail-CI-v4 EAp2: Minimum Energy Performanceposted by on Oct 22, 2024, 2:21 am
Dear all, We’re currently simulating for only one store area in a department building pursuing LEED v4 Certification. The project has received the following observations from... Last reply: Iqbal Khalilullah, Oct 22, 2024, 7:27 pm |
|
EQc Low Emitting Materials- butyl sealant that meets requirementsNC-v4 EQc2: Low-emitting materialsposted by Theresa Lehman on Oct 21, 2024, 5:07 pm
The subcontractor supplying the commercial kitchen equipment for a project included a sealant (Premier XtraBond 1500NS) in their submittal that is not compliant with the LEED EQc Low-Emitting... Last reply: Kimberly Lombardozzi, Oct 22, 2024, 2:12 pm |
|
Fire alarm cables (Public Address system) in the hospitalsHealthcare-v4 MRc6: PBT source reduction - lead, cadmium and copperposted by Najam Us Saqib on Apr 7, 2022, 2:54 am
Fire alarm cables are same like electrical cables, however, its function is different. The v4 LEED guide uses the words ''Electrical wiring and cabling'' under Lead requirements (... Last reply: Michelle Bombeck, Oct 22, 2024, 11:52 am |
|
Defined terms used in the credit language must be clearly identifiedLEED v5 BD+C/ID+C: Overall and Appendix 2nd Public Commentposted by Glenn Heinmiller on Oct 20, 2024, 6:01 pm
I understand that definitions of defined terms are being moved to the reference guide. Therefore it becomes extremely important that defined terms be clearly identified in the credit language... Last reply: Emily Purcell, Oct 22, 2024, 10:00 am |
|
Sky type for Option 2: IlluminanceNC-v4.1 EQc7: Daylightposted by Junaid Mujahid on Oct 7, 2024, 2:17 am
If anyone has used IES-VE's RadianceIES application for Daylight Simulation Option 2: Illuminance, what sky type within RadianceIES should be selected for demonstrating compliance? ... Last reply: Christopher Widdowson, Oct 21, 2024, 2:53 pm |
|
Utilize emergency generator for peak demand reductionNC-v4.1 EAc4: Grid Harmonizationposted by Brightworks Sustainability on Oct 19, 2024, 5:54 pm
Hello, The project includes fossile fuel based emergency generator. Can we utilize the energency generator to comply with GH credit intent? Last reply: Marcus Sheffer, Oct 21, 2024, 1:52 pm |
|
Design for Indoor Air Quality and Infection ControlPilot-Credits EQpc124: Performance-based indoor air quality design and assessmentposted by Rihab Joucht on Oct 21, 2024, 10:40 am
Hello everyone! I'm pursuing this pilot credit for a LEED v4 NC warehouse building and office, located in Longueuil. Any tips to share ? |
|
LTc4 and buildable landNC-v4 LTc4: Surrounding density and diverse usesposted by Jacopo Cattaruzzi on Oct 21, 2024, 8:33 am
Hi, I am following a project of a hotel complex located in the Italian alps. We are aiming at achieving points from LTc4 opt. 1 and I am a bit confused about... |
|
Measurement and Verification for v4 or v4.1NC-v4.1 EAc3: Advanced Energy Meteringposted by Mu'ath Ad on Oct 19, 2024, 6:12 am
Hi, is Measurement and Verification plan still required for v4 or v4.1? can someone brief what is required in this plan and in which credit to refer to for this plan? Thanks Last reply: Marcus Sheffer, Oct 19, 2024, 12:58 pm |
|
14 days VOC Emissions RateCI-v4 EQc2: Low-emitting materialsposted by Alokmay Behera on Oct 19, 2024, 6:45 am
One of the internal paints in the project is Greenguard Gold Certified. The... |