Hi, is Measurement and Verification plan still required for v4 or v4.1?
can someone brief what is required in this plan and in which credit to refer to for this plan?
Thanks
Forum discussion
NC-v4.1 EAc3: Advanced Energy Metering
Hi, is Measurement and Verification plan still required for v4 or v4.1?
can someone brief what is required in this plan and in which credit to refer to for this plan?
Thanks
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5902 thumbs up
October 19, 2024 - 12:58 pm
M&V Plans were required for this credit under LEED 2009. They are no longer required in v4/v4.1.