Topic | Recent |
---|---|
View to indoor gardenCI-v4.1 EQc8: Quality Viewsposted by Michael on Mar 22, 2022, 12:20 am
Hi LEED experts, about "Views into interior atria may be used to meet up to 30% of the required area". Does that mean a room with no view to the exterior but has a view to the indoor garden, can... Last reply: Emily Purcell, Mar 22, 2022, 9:15 am |
|
Baseline Case Outdoor Air ModelingNC-v4 EAp2: Minimum Energy Performanceposted by Mankisha Veng Veng on Mar 17, 2022, 2:58 am
Dear Concern:- Our Design project does not have DCV (Demand Control Ventilation ) so can we model the fresh air identically Baseline and prposed case as per ASHRAE 90.1.2010 ... Last reply: Cory Duggin, Mar 21, 2022, 12:17 pm |
|
How is the requirement for a warehouse different from a new construction?Warehouses-NC-v4.1 LTc8: Electric Vehiclesposted by Alex Edwards on Mar 15, 2022, 5:45 am
Hi! |
|
Historical Rainfall Data- Input for CalculatorNC-v4 SSc4: Rainwater managementposted by Hieu Huynh on May 30, 2019, 8:27 am
Hi LEED experts, It is difficult to find rainfall data of 10 years in my country. I'm just lucky to find an international source for that long data. But they just recorded the average rainfall... Last reply: PARITALA sudhakar, Mar 13, 2022, 12:18 pm |
|
Car Showroom- LEED BD+C: New Construction or Retail?LEED Rating System Selectionposted by Michael on Feb 21, 2022, 11:53 am
Hi LEED experts, My project is a car showroom, where the building owner displays their cars to sell to customers. The building has a workshop area to repair cars. And there are some office and ... |
|
Smoking Area at level 2NC-v4 EQp2: Environmental tobacco smoke controlposted by Wah Wah on Jan 7, 2022, 4:36 am
Hello all, One of out project is pursuing LEED BD+C for new construction. The building has a open garden at level 2. Is it allowed for us to provide a designated smoking area there... Last reply: Afogreen Build, Feb 17, 2022, 1:58 am |
|
What exactly Accessible Flooring means herewith in this credit language?CI-v4.1 MRc2: Interiors life-cycle impact reductionposted by Jeevan Doifode on Jan 25, 2022, 4:49 am
For general office building which typically has flooring system with ceramic tiles and floorboxes for Data/voice.What exactly Accessible Flooring means herewith in this credit language? Last reply: J Schütz, Jan 28, 2022, 9:27 am |
|
Zero lot line DefinitionNC-v4 SSp1: Construction Activity Pollution Preventionposted by Alex Edwards on Dec 30, 2021, 2:42 am
Hi All! I read the definition of zero lot line and have a question, does the basement count as construction area? Last reply: Jose Gonzalez, Jan 9, 2022, 7:05 pm |
|
Potential non-compliance with regulationNC-v4 EAp1: Fundamental commissioning and verificationposted by Timothy Ian Middleton on Dec 8, 2021, 6:13 am
Our... Last reply: Timothy Ian Middleton, Dec 22, 2021, 11:01 pm |
|
LEED rating for warehouseNC-v4 MPR2: Must use reasonable LEED boundariesposted by Alex Edwards on Dec 21, 2021, 10:17 am
Hi all, thanks for help! |