Decorative lightingHospitality-NC-v4 EAp2: Minimum Energy Performanceposted by Ricardo Sá on Nov 22, 2022, 7:14 am
Dear all, we’re currently involved in several hospitality projects pursuing LEED certification. We have a doubt related with energy performance calculations, namely in what relates... Last reply: Marcus Sheffer, Nov 22, 2022, 11:20 am |
|
How to calculate / count the multi occupant space???NC-v4 EQc6: Interior lightingposted by SAMY Chamy on Nov 21, 2022, 6:19 am
Hi all, I have some clarification in counting the multi-occupant space in the canteen and meeting area. because the canteen has a seating capacity of 200 (50 tables X 4 seats for... Last reply: Maria Porter, Nov 21, 2022, 7:07 am |
|
IPpc100 Passive Survivability and Functionality during EmergenciesNC-v4 INc1: Innovationposted by Noriko Nagazumi on Jan 29, 2019, 2:44 am
Hi, We are submitting this pilot credit via Option 2: Provide Backup Power for critical loads. The project building is office usage, but there is no instruction for office building... Last reply: Kelvin Chan, Nov 20, 2022, 12:00 pm |
|
Surrounding Density and Military BarracksNC-v4 LTc4: Surrounding density and diverse usesposted by Anthony Taibi on Nov 9, 2022, 3:56 pm
the dwelling unit factor is determined by the zoning- correct? what is the zoning for military bases? we work on barracks. Last reply: Emily Purcell, Nov 18, 2022, 4:47 pm |
|
When a material data sheet does not have SRPilot-Credits SSpc154: Heat Island Mitigation with Cool Wallsposted by Mariana Guevara on Nov 17, 2022, 5:13 pm
Sometimes a material data sheet does not have SR and or TR. Is there a material standard that can be used as refrence to obtain the SR and TE values? Before, on LEED v3 BD+C - SSc7.1... |
|
Building less than 100 m from High-capacity Transit Hub- Is a bicycle network still required?NC-v4.1 LTc6: Bicycle facilitiesposted by Hatim Mustafa on Nov 17, 2022, 4:19 pm
Hi everyone! We have a very interesting situation at hand. Our building is targeting LTc6 - Bicycle Facilities, the project is located in an area that does not have a... |
|
Electronic Signage- Green Building EducationNC-2009 IDc1: Innovation in Designposted by UO Design and Construction on Mar 16, 2018, 5:11 pm
Hello, We are wondering if a touch screen tablet (permanently installed in a highly visible part of the building) that displays both energy use data as well as building sustainability... Last reply: Megan Bodin, Nov 17, 2022, 2:03 pm |
|
v4.1 O+M: working with a new buildingLEED v4.1 Discussion Forumposted by Victoria Rios Esteve on Nov 17, 2022, 1:44 pm
Hi everyone, Hope you are well. We were requested to work on a LEED v4.1 O+M: Existing building certification. This building has 30yo. It has been under a major renovation. We wanted to... |
|
Ozone MonitoringLEED v4.1 Discussion Forumposted by Sharon Bessa on Nov 17, 2022, 10:57 am
Is the Aeroqual OZL approved for ozone testing? |
|
Does Boston's MBTA Silver Line count as Bus Rapid Transit?NC-v4 LTc5: Access to quality transitposted by Eric Dammeyer on Nov 17, 2022, 9:27 am
Our team is working on a project in Boston located near the MBTA Silver Line (0.46 miles from the Silver Line Way stop). The bus system runs in a dedicated transit tunnel from Silver Line Way to... |