Design of flexibility- Can an open ceiling be counted as an accessible ceiling?

CI-v4 MRc2: Interiors life-cycle impact reduction
posted by Michael on Apr 4, 2022, 2:54 am

Hi LEED experts, my interior Office wants to have an open ceiling, where people can see and access the piping, ductwork system, and HVAC machines hanging below the ceiling...

Last reply: Sarah Buffaloe, Apr 15, 2022, 12:18 pm

CMP reporting

LEED Exam Discussion
posted by Ashraf Elghetany on Jun 23, 2020, 10:38 am

Hello,

I am LEED AP BD+C and yesterday passed my well AP. from the CMP guide the 24 hours genereal can be reported for both LEED and WELL. my question here ..can i report my study and well...

Last reply: sana salman, Apr 15, 2022, 3:29 am

Off Site Renewable Energy Purchase

NC-v4 EAp2: Minimum Energy Performance
posted by SAMY Chamy on Apr 13, 2022, 2:28 pm

Dear Concern:-

I have purchased renewable electrical energy from the nearest solar power plant as Kwh so I have to get a point in Renewable energy via Tier 2 because the solar...

Last reply: SAMY Chamy, Apr 14, 2022, 3:04 pm

Project type

LEED v4.1 Discussion Forum
posted by akshaya bhaskar on Apr 13, 2022, 11:40 am

We are currently in the porcess of designing a park shelter/pavillion that is about 4500 sqft in an existing park. The shelter will have a block of toilets, a bookable community space (indoor and...

Last reply: Dave Hubka, Apr 13, 2022, 4:10 pm

Recycled content for FSC wood.

CI-v4.1 MRc4: Sourcing of Raw Materials
posted by Tracy Backus on Apr 13, 2022, 11:21 am

On LEED v4.1, can you count the...

Last reply: Dave Hubka, Apr 13, 2022, 4:08 pm

Off Site Windmill & Purchase Electricity from Solar PV Plant for Project

NC-v4.1 EAc5: Renewable energy
posted by Mankisha Veng Veng on Apr 7, 2022, 5:22 am

Dear Concern:-

we have project in Industrial Zone here we done have possibility of install the Windmill in Project site and additionally we done have enough space at project to install...

Last reply: SAMY Chamy, Apr 13, 2022, 2:35 pm

Option 2:Only CO2 sensors

CS-v4 EQc1: Enhanced indoor air quality strategies
posted by Dina El-Sady on Apr 11, 2022, 6:48 am

The project is totally mechanically ventilated .I am choosing adding CO2 sensors in dense areas for option 2 for additional...

Last reply: Michelle Rosenberger, Apr 13, 2022, 10:12 am

Are all project parking spaces to be included in the count for an Addition, or just the new spaces designed for the Addition?

NC-v4.1 LTc8: Electric Vehicles
posted by Mollie O'Rourke on Mar 23, 2022, 8:48 pm

We have a project with a 4-story horizontal addition being added (it is actually a healthcare facility, but there are not currently any Q/A's in the HC Forum).  Being helathcare, there is a large...

Last reply: emily reese moody, Apr 12, 2022, 12:34 pm

eQuest can't define steam Loop

NC-v4 EAp2: Minimum Energy Performance
posted by Kathy Collins, LEED AP , WELL AP on Mar 10, 2022, 5:38 pm

We have a project that there are two steam plants, one for dehumidifier and processed steam. We have rack washers that use Steam and electricity to do the job. These rack washers are fed by Steam...

Last reply: Tyler Thumma, Apr 12, 2022, 9:55 am

Baseline Design Supply Airflow Rate Temperature Difference 90.1-10 para. G3.1.2.9.1

NC-v4 EAp2: Minimum Energy Performance
posted by Michael Callan on Mar 30, 2022, 1:27 pm

Hello,

I have a qeustion regarding ASHRAE 90.1-10, paragraph G3.1.2.9.1 which states that for baseline systems 1through 8, design supply airflow rates for the baseline building shall be...

Last reply: Tyler Thumma, Apr 12, 2022, 9:47 am