Industrial Process Loads and the Exceptional Calulation MethodNC-2009 EAc1: Optimize Energy Performanceposted by Jeff Ross-Bain, PE, LEED Fellow, WELL AP on Apr 16, 2014, 4:22 pm
We have an industrial plant where the process loads are assumed to be, say, 98% of all building energy use. Therefore, even if the non-process building portion was Net Zero Energy, we would not... Last reply: Abdullah Tahir, Mar 25, 2024, 1:39 am |
|
Modeling only conditioned areaNC-v4 EAp2: Minimum Energy Performanceposted by Omar Elrawy on Dec 9, 2020, 10:05 pm
I'm certifying a huge factory with an attached office building. Is it possible to model only the office area? Last reply: Abdullah Tahir, Mar 25, 2024, 1:38 am |
|
Walk off mats for skyway entranceNC-v4 EQc1: Enhanced indoor air quality strategiesposted by SIG - Sustainability Main Account on Mar 22, 2024, 2:34 pm
Would a skyway, those elevated walkways between buildings popular in Minneapolis, be considered a "... Last reply: Talia Mamayek, Mar 22, 2024, 4:16 pm |
|
Storage locationNC-v4 MRp1: Storage and Collection of Recyclablesposted by Maiz Rech on Sep 11, 2023, 1:33 pm
Is there a minimum distance or positioning requirement for this area? Would it be a problem to locate the recyclables storage on the building underground floor? Last reply: Thomas Lagarde, Mar 22, 2024, 2:28 pm |
|
Buildings within site but not under LEED scopeNC-v4 EQp2: Environmental tobacco smoke controlposted by Marwa Elzoghby on Mar 22, 2024, 10:44 am
I have a project where the driver room and canteen, situated at the main gate, are not part of the LEED scope. Given their proximity to the LEED boundary, I am wondering whether it's necessary to... |
|
Building Envelope CommissioningNC-v4 EAc1: Enhanced Commissioningposted by Chris Bennett on Feb 16, 2018, 5:29 pm
Hello All, Has anyone gone through the process of building envelope... Last reply: sooha ham, Mar 21, 2024, 4:09 am |
|
Gross Floor AreaCI-v4 MPR3: Must comply with project size requirementsposted by Edgar Arevalo on Mar 21, 2024, 3:09 pm
For a LEED Commercial Interior fit-out project, when we are registering the project in LEED Online it asks for the gross square footage. Since... |
|
Can EC3/TallyCAT be used for Option 3: Building Interiors Life Cycle Assessment?CI-v4.1 MRc2: Interiors life-cycle impact reductionposted by Nikhita Sapuram on Aug 8, 2023, 12:03 pm
Most WBLCA software programs do not include product specific data. For a tenant improvement project would it be acceptable to use a program that only looks at environmental impacts from cradle to... Last reply: Kate Holly, Mar 21, 2024, 2:32 pm |
|
Exterior Illuminated SignageEBOM-v4 MRc2: Purchasing - lampsposted by Kristina K on Mar 21, 2024, 11:37 am
Hello, Does this credit apply to Exterior Illuminated Signage? Thank you |
|
Total Material CostLEED v4.1 Discussion Forumposted by Arda Buyuklu on Mar 21, 2024, 10:49 am
Why is providing Total Material Cost required/necessary when completing a LEED v4.1 Materials Reporting Form? How is this relevant for LEED purposes, especially if it is almost always subject to... |