Commissioning Documentation for 7 separate towers sharing a common ground floor & podium level with shared/mixed MEP Systems

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Joshua ADY on Mar 10, 2019, 6:24 am

We are working as an independent...

Last reply: Scott Bowman, Aug 11, 2019, 6:23 pm

Phased Cx for a phased project

NC-v4 EAp1: Fundamental commissioning and verification
posted by Peter Doo on Apr 15, 2019, 4:55 pm

We are working on a comprehensive renovation and addition of an Art Center at an independent high school. The project will be phased; existing system upgrades and building renovation in phase 1...

Last reply: Scott Bowman, Aug 11, 2019, 6:13 pm

Envelope CxA within the engineering company part of design team?

NC-v4 EAc1: Enhanced Commissioning
posted by Erika Roy on Apr 23, 2019, 1:59 pm

Hello,

We want to use a building envelope...

Last reply: Scott Bowman, Aug 11, 2019, 6:09 pm

Envelope Design Review for LEED V4 Commissioning under Fundamental Cx

NC-v4 EAp1: Fundamental commissioning and verification
posted by Rohit Upadhyay on Apr 24, 2019, 7:55 pm

Hi Everyone,

Can someone clarify what is the extent of envelope design review by a Commissioning Authority (...

Last reply: Scott Bowman, Aug 11, 2019, 6:06 pm

BOD review from the BECx consultant

NC-v4 EAc1: Enhanced Commissioning
posted by Julie Trottier on Jun 4, 2019, 11:44 am

Good Morning,

In order to pursue the EAc1 option 2 , we are the building envelope...

Last reply: Scott Bowman, Aug 11, 2019, 6:01 pm

"durability"

NC-v4 EAp1: Fundamental commissioning and verification
posted by Tom Kennedy on Jun 5, 2019, 6:39 pm

The Pre-req...

Last reply: Scott Bowman, Aug 11, 2019, 5:56 pm

Enhanced Commissioning

NC-v4 EAp1: Fundamental commissioning and verification
posted by saif eddine majdaoui on Jun 25, 2019, 2:26 am

We are working on a big project, we are the LEED subcontractor (consultant) of the general contractor (All trades), 
The owner gave all LEED responsibilities to the general contractor, so...

Last reply: Scott Bowman, Aug 11, 2019, 5:49 pm

Commissioning of Existing Equipment

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Jatuwat Varodompun on Jul 22, 2019, 1:24 am

We have a major renovation project which is 40% of gross area. Do we need to...

Last reply: Scott Bowman, Aug 11, 2019, 5:37 pm

CS EA credit Enhanced Cx- who can serve as CxA

CS-v4 EAc1: Enhanced Commissioning
posted by Deeta Bernstein on Jul 22, 2019, 2:08 pm

Any precedent in pursuing the Enhanced...

Last reply: Scott Bowman, Aug 11, 2019, 5:30 pm

EAp1-Fundamental Commissioning and Verification- OPR / BOD

NC-v4 EAp1: Fundamental commissioning and verification
posted by Maria Peralta on Jul 26, 2019, 3:38 am

Hello, I have a question regarding the...

Last reply: Scott Bowman, Aug 11, 2019, 5:26 pm