I am working on a multiphase project where each phase has dramatically different scopes of work for the project and each has a different GC. Would it be more correct to submit one waste management plan that compiles all of the information from each phase or three seperate plans?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Afogreen Build
www.afogreenbuild.comGreen Building Consultant
247 thumbs up
April 16, 2024 - 9:00 pm
Hi Biake,
There is no written information that waste management plan in multiphase building should be separated. On page 481, LEED BD+C v4 guide only states that the Construction and Demolition Waste Plan (CDMP) must include an overall project waste diversion goal.
So, it should be better if the plan compiles all the information from each phase.
Best regards – Afogreen Build Team