I am working on a multiphase project where each phase has dramatically different scopes of work for the project and each has a different GC. Would it be more correct to submit one waste management plan that compiles all of the information from each phase or three seperate plans?
www.afogreenbuild.com
Green Building Consultant
LEEDuser Premium Member
249 thumbs up
Wed, 04/17/2024 - 01:00
There is no written information that waste management plan in multiphase building should be separated. On page 481, LEED BD+C v4 guide only states that the Construction and Demolition Waste Plan (CDMP) must include an overall project waste diversion goal. So, it should be better if the plan compiles all the information from each phase.