INpc138 Safety First Pilot Credit TransitionPilot-Credits INpc138: Managing Indoor Air Quality for Infection Controlposted by Barry Abramson on Mar 8, 2023, 6:01 am
We have pursued this pilot credit several times for client buildings. It was extremely relevant during the height of the pandemic but has ongoing importance. Very pleased that USGBC has... |
|
permanently installed building productsWarehouses-NC-v4.1 MRc3: Sourcing of Raw Materialsposted by Cecile de Villemeur on Mar 7, 2023, 1:08 pm
Hello, Could you tell me which products should be included in the permanently installed building products ? I think that technical equipment (HVAC or electric) shouldn't be included... Last reply: Cecile de Villemeur, Mar 7, 2023, 4:16 pm |
|
Pilot Credit: Carbon sequestration through on site plantingNC-v4 INc1: Innovationposted by Emily Purcell on Mar 7, 2023, 11:43 am
I have calculated this credit for a few projects and am sharing my comments: - Overall the calculator is easy to use. On urban projects with limited landscaping area, it can be challenging... Last reply: Deborah Lucking, Mar 7, 2023, 12:06 pm |
|
EV Charger has demand response capability but is not Energy StarNC-v4.1 LTc8: Electric Vehiclesposted by Jeff Ross-Bain, PE, LEED Fellow, WELL AP on Mar 7, 2023, 11:53 am
Hi All, To clarify language for this credit, does "Meet the connected functionality criteria for ENERGY STAR certified EVSE and be capable of responding to time-of-use market signals (... |
|
Existing MultiFamily High Rise-Exclude Occupied Commerical SpaceHealthcare-v2009 MPR3: Must use a reasonable site boundaryposted by Laura Steinbrink on Aug 11, 2016, 8:29 am
We have an existing 13 Story Downtown Multifamily LEED NC v2009 registered project consisting of 210,000 sf and 200 units which will be gutted. The ground floor has approximately 5 commercial/... Last reply: Lusjena Cakeri, Mar 7, 2023, 11:30 am |
|
Core & Shell mandatory provisionsCS-v4 EAp2: Minimum Energy Performanceposted by Julio Fernandez Amodia on Mar 6, 2023, 1:46 pm
Hi to all, I am currently assessing a mall LEED compliance. This is a C&S LEED project with retail units as tenant spaces where the owner has no control. I was wondering if the ASHRAE... Last reply: Ashish Nautiyal, Mar 7, 2023, 11:27 am |
|
Project is not required to simulate baseline in 4 orientationsNC-v4 EAp2: Minimum Energy Performanceposted by Michael on Feb 16, 2023, 2:57 am
I would like to understand the line: the project is not required to simulate 4 baseline orientations because the building orientation is dictated by the site consideration. What does "Site... Last reply: Marcus Sheffer, Mar 7, 2023, 10:07 am |
|
Vegetation above underground rainwater harvesting tankData-Centers-NC-v4.1 SSc2: Protect or Restore Habitatposted by Y Nguyen on Mar 7, 2023, 5:48 am
Hi all, My question is regarding a landscape area calculation for Data center project. Currently design, the landscape area is including around 11% vegetation area above... |
|
Does Option 2 apply to LEED for Retail?Retail-NC-v4 EQc6: Interior lightingposted by Deborah Lucking on Jul 1, 2019, 4:52 pm
Here is the Credit language "For at least 90% of the individual occupant spaces in office and administrative areas, provide individual lighting controls. In sales areas, provide controls that can... Last reply: Martin Maribo, Mar 7, 2023, 8:00 am |
|