I am trying to pursue Green Power and Carbon Offsets credit. I am curious as to the date of the cotnract- can the RECs be purchased during construction or does it have to be from substantial completion forward?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for $... »
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5925 thumbs up
April 24, 2020 - 2:18 pm
You have the cover the required timeframe starting at occupancy.
Nadia Bini
Sustainability CoordinatorMSDL Architectes
3 thumbs up
March 7, 2025 - 2:59 pm
Hello Marcus and Carolina, can you please clarify ?
Does the 5 year time frame need to include the occupancy date, or do the RECS have to START at substancial completion/occupancy?
We would like to buy during construction on a 2-year construction timeline, and want to make sure we are not penalized by purchasing too early...
Thanks for your follow-up!
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5925 thumbs up
March 8, 2025 - 11:53 am
They should start at occupancy.