Cradle to cradle certificate as ACP?
NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systemsposted by Isolda Strom on
Dear All, I am working on a LEED project in Europe. Our architect is applying several products with Cradle to cradle certificates.
Mandatory provisions for a heat pump
NC-2009 EAp2:Minimum Energy Performanceposted by Francesco Passerini on
I have to model a heat pump that outside the building exchanges heat with the external air and it exchanges heat with the building, i.e. with the internal part of the HVAC plant, thorough water.
Water Efficient landscaping - finding the ETo
NC-2009 WEc1:Water Efficient Landscapingposted by Robert Thomas, CPD, LEED AP BD+C on
How can I find the evapotranspirtaion rate, ETo, for various plants in various regions, and can this be found on LEEDuser's website?
Would this apply to International Projects too ?
posted by Mike Barker on
Does this apply to projects outside continental USA ? And about Alternative Compliance Paths in particular ?
Two hotels, same Developer, but not connected. Rating System?
posted by Jay Murray on
Hi. Two brand new hotels in Boston in conceptual design now, one is 200,000 sf, the other is 150,000 sf. They are separated by a street (also owned by the developer).
Calculating peak occupancy
posted by Alexia Anastassiadis on
We are working on a project with 4 different shifts. One regular 8 to 5 shift for office and morning afternoon and night shifts for factory workers, there no transients or visitors.
Mechanical plans ando/or drawings
NC-2009 PIf4:Schedule and Overview Documentsposted by JOSE R. TAGLE on
Hello, I'm on a New Construction project and Preform4 asks for Mechanical plans and/or drawings, i'm not sure if these refer to HVAC plans only, or if it includes other plans such as MEP ones (HVAC
Renovation of 3rd Floor Surgical Suite in Four Story Hospital
posted by Jeff Russell on
I am designing a renovated surgical suite consisting of 39,789 sf of project area. The total floor plate is 103,223 sf. The building is type I construction with a primary I-2 Occupancy.
How many credit points does one get by offsetting 7%.
CS-2009 EAc2:On-site Renewable Energyposted by Tuana Papile on
By using on-site renewable energy for 7% of the total energy, do we get now 7 points compared to the 4 points for NC? Thank you
Control of verhead lighting through VOIP phone integration
NC-2009 IEQc6.1:Controllability of Systems—Lightingposted by Saju Varghese on
Would VOIP phone integration lighting controllability of individual workstations (in open offices) count towards the credit, instead of using task lighting?