Automatic Light Shut-off for the Whole Building

CI-2009 EAp2: Minimum Energy Performance
posted by Dee Spiro on Jun 30, 2010, 10:29 am

In Section 9. Lighting Requirements (ASRAE 90.1-2007) on page 141 of the reference guide, in the third paragraph it states that Section 9.4 describes the mandatory provisions for controls,...

Last reply: Paul Conrad, Jun 30, 2010, 10:39 am

In the lease, but not in the scope

CI-2009 EAp2: Minimum Energy Performance
posted by Dee Spiro on Jun 24, 2010, 1:05 pm

For prescriptive compliance, is a CI project required to meet continuous insulation requirements for building envelope if it is not part of their project scope, even if there is nothing in the...

Last reply: Paul Conrad, Jun 28, 2010, 9:45 am

A question on Mandatory Provisions

CI-2009 EAp2: Minimum Energy Performance
posted by Jose Salinas on May 26, 2010, 5:32 pm

I am working on a CI for three floors of a new existing building, non-LEED certified.
We are developing a computer simulation so we have to document the ASHRAE Mandatory provisions only. (...

Last reply: Paul Conrad, Jun 11, 2010, 9:01 am

Confused on what to fill in on the ASHRAE Buiding Envelope Compl

CI-2009 EAp2: Minimum Energy Performance
posted by Sarah Johnson on May 21, 2010, 2:40 pm

We are doing a LEED CI upfit in an old existing building. The upload page for EAp2 requires that we upload ASHRAE Buiding Envelope Compliance form. The Envelope is not in the scope of the...

Last reply: Paul Conrad, May 27, 2010, 8:47 am

ASHRAE Compliance Forms

CI-2009 EAp2: Minimum Energy Performance
posted by Jose Salinas on Apr 19, 2010, 9:49 am

Hi, my question is as follows: in version 2.2 when you chose to use the complience forms to support the mandatory provisions, only the check list part was necessary to be filled up. Since the V 3...

Last reply: Paul Conrad, May 27, 2010, 8:45 am

ASHRAE 90.1 Space by Space Increase in Power Allowance.

CI-2009 EAp2: Minimum Energy Performance
posted by Christopher Shaw on May 13, 2010, 11:44 am

How does the increase in power allowance described in 9.6.2 work?
Firstly, how decorative is decorative. Do pendant fixtures hanging over a reception desk, which while intended as...

Last reply: Erik Dyrr, May 13, 2010, 1:28 pm

Commercial Interiors version 3 EAp2

CI-2009 EAp2: Minimum Energy Performance
posted by Jordi Monjo on Jan 27, 2010, 11:08 am

Hello,
the project is a restaurant focused on wine, located in Barcelona (Spain). We’ve got many problems in finding Energy star certified products in European market for many applications...

Last reply: Erik Dyrr, Mar 29, 2010, 12:05 pm

CA title 24

CI-2009 EAp2: Minimum Energy Performance
posted by Doug Drynan on Nov 9, 2009, 2:27 pm

When utilizing CA Tilte 24 as the referenced standard, will this meet the requirements of this prerequisite for mandatory and prescriptive requirements and lighting power...

Last reply: Erik Dyrr, Mar 29, 2010, 12:00 pm

CA Title 24

CI-2009 EAp2: Minimum Energy Performance
posted by Doug Drynan on Dec 13, 2009, 11:00 pm

It would be very helpful if you could provide detailed guidance on how to complete the LEED documention for projects choosing the CA Title 24-2005, Part 6 compliance path. When using the...

Last reply: Erik Dyrr, Mar 29, 2010, 11:54 am

Factory in Vietnam

CI-2009 EAp2: Minimum Energy Performance
posted by Fabio Frescia on Dec 8, 2009, 5:14 am

I have a US client that is renting a space inside an existing factory to put in it his laundry facilities services. It's a part of a big warehouse, all a big environment, so it won't be possible...

Last reply: Shillpa Singh, Dec 9, 2009, 8:40 am