We are doing a LEED CI upfit in an old existing building. The upload page for EAp2 requires that we upload ASHRAE Buiding Envelope Compliance form. The Envelope is not in the scope of the upfit, so my understanding is that we don't have to do anything to it, or report anything about it. What are we supposed to fill in on the form? It seems like we shouldn' t have to upload it, but do they just want the form with the project name, etc. and nothing checked?
Thanks,
Sarah Johnson
10 thumbs up
May 25, 2010 - 12:02 pm
Anybody out there?
Sarah Johnson
10 thumbs up
May 25, 2010 - 2:54 pm
Thanks, I've been searching on the web and haven't found anything yet.
Paul Conrad
Energy EngineerCLEAResult Consulting
346 thumbs up
May 27, 2010 - 8:47 am
Sarah,
If the building Envelope is not part of your scope, then I would upload a short document in it's place explaining that it's not part of your scope and therefore no document has been provided.
Paul