Concrete forming and temporary material- recycled content

NC-2009 MRc4: Recycled Content
posted by Caroline PIN on Sep 17, 2014, 5:25 am

sense and is straight from the credit language. However, there's been discussion on this forum about contractor overhead being applied to the relevant divisions, such that the 45% is multiplied...

Last reply: Geoffrey Brock, Sep 25, 2014, 10:08 am

Hard-Lid Ceiling

NC-2009 IEQc5: Indoor Chemical and Pollutant Source Control
posted by Omar Elrawy on Nov 5, 2014, 8:57 am

Dear all,
I need to know exactly what fulfills the "Hard-lid" ceiling?. I have a false ceiling with gypsum board partitions all over the floor; I need to know - for example -...

Last reply: Jon Clifford, Nov 11, 2014, 7:48 am

Need your Advise- Urgent (Sports Hall Project)

NC-2009 EAp2: Minimum Energy Performance
posted by SSN Energy Model on Feb 11, 2016, 6:31 am

Hi,

We are doing Energy Simulation for Sports Hall Project (G+1 Story building). Sports hall having single playing court and it will be used for various sports activities. Sometimes, it...

Last reply: Marcus Sheffer, Mar 7, 2016, 3:54 pm

Intelligent Glazing

NC-2009 IEQc8.1: Daylight and views - daylight
posted by Peter Sushch on Jun 6, 2016, 3:57 pm

For the majority of our project we are using intelligent, electrochromic windows that automatically tint to maximize natural light. How should we go about calculating and documenting daylighting...

Last reply: Renee Azerbegi, Aug 30, 2016, 10:48 am

Daylight Analysis

NC-2009 IEQc8.1: Daylight and views - daylight
posted by SAMY Chamy on Jun 15, 2016, 8:03 am

Dear All

we have done daylight analysis for factory building.

we get daylight of 85% in 9 AM and 73 % in 3AM (Date -21 - September)

In this case which value we take to enter...

Last reply: GBD Architects, Sep 13, 2017, 12:18 pm

Vague extraction location distance

NC-2009 MRc5: Regional Materials
posted by Edgar Arevalo on Aug 26, 2019, 11:08 am

I have been receiving LEED material forms along with submittal documents for each materials where they provide an exact distance between the manufacturing site and the project site, but when it...

Last reply: Edgar Arevalo, Aug 27, 2019, 3:48 pm

Alternate Compliance Path for 50% Energy Star Rated Equipment?

CI-2009 EAp2: Minimum Energy Performance
posted by Nancy Henderson on Mar 1, 2010, 1:02 pm

Does anyone know if there is an approved alternate compliance path for meeting the 50% Energy Star Rated equipment portion of this prerequisite? We have a client with hundreds of pieces of...

Last reply: Lauren Sparandara, Jul 13, 2010, 12:28 am

ASHRAE 90.1 mandatory provisions

CI-2009 EAp2: Minimum Energy Performance
posted by Adam Targowski on Aug 10, 2012, 10:30 am

We were asked to make a preassessment of a project which wants to get LEED CI certification. The tenant's scope of work includes only small alterations of the space like moving some of the...

Last reply: JOHN BURNETT, Feb 14, 2013, 4:48 am

Proving compliance for a C&S project

CS-2009 IEQc6: Controllability of systems - thermal comfort
posted by Maya Karkour on Sep 14, 2010, 11:58 am

Hello,

Our project is a C&S office and the furniture layout is not yet known. The cooling and heating system will consist of a VRV. Thermostats and other controls will be installed...

Last reply: Lauren Sparandara, May 31, 2013, 1:21 pm

Tankless Electrical Water Heaters

CS-2009 EAp2: Minimum Energy Performance
posted by Pedro Urazan on May 11, 2016, 10:51 am

Hi,

Do tankless Electrical water heaters have to comply with any efficiency requirements, in order to comply with the 7.4 mandatory provisions? On table 7.8 the performance requirements...