posted by Heather Appell on Jul 23, 2019, 1:12 pm

Has anyone tried to pursue LEEDv4 LT High Priority Site as an alternative compliance path for SSc3...

Last reply: Dave Hubka, Jul 23, 2019, 7:42 pm

Remediation done by previous owner as part of purchase agreement

NC-2009 SSc3: Brownfield Redevelopment
posted by on May 22, 2019, 2:22 pm

If the building owner purchased the building with the remediation done as part of the purchase agreement by the prior owner can they still receive this credit?

Last reply: Larry Sims, May 23, 2019, 7:11 am

ASTM E1903-97 Phase II Environmental Site Assessment- Local Equivalent documentation

NC-2009 SSc3: Brownfield Redevelopment
posted by Adrie Fourie on Sep 29, 2017, 6:53 am

We are involved with a project outside of the US that undertook a...

Local voluntary cleanup program- definition

NC-2009 SSc3: Brownfield Redevelopment
posted by Anna Korinkova on Mar 9, 2017, 9:54 am

Under Option 1 of the credit, we can pursue EITHER the...

Last reply: Larry Sims, Mar 13, 2017, 12:52 pm

Asbestos Remediation

NC-2009 SSc3: Brownfield Redevelopment
posted by Jeannie Rueter on Mar 7, 2016, 11:51 am

The first phase of our Job Corps project was to construct a new cafeteria on campus. The second phase is to demolish the old cafeteria. The old cafeteria has asbestos in it. Can the abatement of...

Last reply: Jeannie Rueter, Mar 9, 2016, 11:29 am

Asbestos Abatement Requirement Compliance

NC-2009 SSc3: Brownfield Redevelopment
posted by UO Design and Construction on Jan 15, 2016, 4:38 pm

We always conduct asbestos surveys (assessments) in accordance with the LRAPA regulations Title 43. LRAPA regulations are similar to...

Last reply: Allison Beer McKenzie, Mar 9, 2016, 10:58 am

Brownfield Documentation

NC-2009 SSc3: Brownfield Redevelopment
posted by Ivan Romero on Aug 11, 2015, 8:11 pm

I've scanned the discussions on...

Last reply: Allen Cornett, Aug 20, 2015, 5:12 pm

Brownfield site but graded before the construction started

NC-2009 SSc3: Brownfield Redevelopment
posted by Michael Wahjudi on Jun 2, 2015, 3:47 am

Our site is brownfield (existing navy base), but the site is being graded before 1980 to be prepared as industrial area. The current construction activity start at 2014. Can we still consider our...

Last reply: Michael Wahjudi, Jun 9, 2015, 12:02 am

Petrol contamination

NC-2009 SSc3: Brownfield Redevelopment
posted by Alicja Bieszyńska on Jan 27, 2015, 3:06 pm

My project site is located next to one of the main arteries of Warsaw. Due to the high trafic the strip adjacent to the road is contaminated with petrol related substances (not much but still)....

Last reply: Susan Walter, Jan 28, 2015, 4:33 pm

State DEQ-Listed Brownfield Site- credit denied

NC-2009 SSc3: Brownfield Redevelopment
posted by Michele Otazua on Jan 21, 2015, 5:19 pm

In our first review, our credit was denied. We are on a zero lot line property with the building occupying the entire site, but the site is listed on the state DEQ register of brownfield sites...