Line of sight to spaces with glass roofsNC-2009 IEQc8.2: Daylight and views - viewsposted by Lauri Tähtinen on Dec 3, 2010, 4:46 am
To be sertain, I want to ask a opinion for a situation, where a office building has vision to inner yard. Basic situation contains two office masses with glass roof covered 35 ft inner yard in... Last reply: Jill Perry, PE, Apr 24, 2011, 6:25 pm |
|
ASHREA Simulation vs. actual building operationsCS-2009 EAc5.1: Measurement and verification - base buildingposted by Susann Geithner on Dec 15, 2010, 6:10 pm
When we enter the calculated consumptions from EA P2 into the EA C5.1 LEED Online form, can I than use other values, which are based on actual building operation and performance? Last reply: Gordon Shymko, Apr 24, 2011, 4:09 pm |
|
Air PollutionNC-2009 SSp1: Construction Activity Pollution Preventionposted by Lu Anne Nielsen on Apr 12, 2011, 3:09 pm
SSp1 was marked under pending for my current project. The review tells me to provide a revised LEED Prerequisite Form that includes a detailed narrative describing the measures taken for the... Last reply: Lisa Fabula, Apr 23, 2011, 11:30 pm |
|
LEED CS 2009- "Cold, Dry, Dark, Shell?"LEED Rating System Selectionposted by Tony Ricketts on Apr 6, 2011, 3:34 pm
We have been asked to provide designs for a... Last reply: Tristan Roberts, Apr 23, 2011, 10:29 pm |
|
To LEED CI or not lead to CI? That is the question...LEED Rating System Selectionposted by anastasia harrison on Apr 20, 2011, 8:36 pm
We have a client who is a state school run by a not-for profit organization. Technically the owner is the state; operator the school, but this can be blurry and perceived as owner/operator.... Last reply: Tristan Roberts, Apr 23, 2011, 10:13 pm |
|
Natural Ventilation- Single SpaceNC-2009 IEQp1: Minimum indoor air quality performanceposted by Omer Moltay on Mar 11, 2011, 11:06 am
Almost all the spaces in our building is mechanically ventilated, except the entrance lobby which receives outside air through revolving doors. The revolving door opening area and the 8 m. rule... Last reply: Tristan Roberts, Apr 23, 2011, 8:58 pm |
|
Reuse of building structureNC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roofposted by Adriana Hansen on Apr 11, 2011, 2:00 pm
Hello, We are working with a major renovation in a stadium. The huge structural external columms will be maintained (100%), but the floor slabs will be demolished, except for some parts of... Last reply: Tristan Roberts, Apr 23, 2011, 8:57 pm |
|
ASHRAE 62.1-2010NC-2009 IEQp1: Minimum indoor air quality performanceposted by Andreas Hintz on Apr 18, 2011, 11:47 am
For this prerequisite it is necessary that the ASHRAE Standard 62.1-2007 is met. But what about the newest version ASHRAE Standard 62.1-2010? Does that one count as well? Thanks for your... Last reply: Tristan Roberts, Apr 23, 2011, 8:49 pm |
|
Irrigation- Baseline caseNC-2009 WEc1: Water Efficient Landscapingposted by Maya Karkour on Mar 7, 2011, 11:52 am
Hello, The guidance is not really clear on what to put in the baseline case. It only says that we need to specify typical landscaping practices. Do we need to document these... Last reply: Tristan Roberts, Apr 23, 2011, 6:01 pm |
|
LEED Documentation- is it required for this pointNC-2009 SSc6.2: Stormwater design - quality controlposted by Kelley Howell on Apr 7, 2011, 5:45 pm
Our project approach to this point is pretty straightforward. We are using a water quality... Last reply: Tristan Roberts, Apr 23, 2011, 5:48 pm |