Points for not having Cooling Tower- System 7- is it possible?CS-v4 WEc3: Cooling tower water useposted by Konstantina Kalliakoudi on Mar 21, 2023, 9:24 am
Hello to all, I have project CS which is nonresidential more than 5 Floors ( System 7 of ASHRAE 90.1- appendix G) and there will be NO cooling tower installed.
|
|
Using microgrid battery storage to achieve demand response crediPilot-Credits EApc8: Demand responseposted by S. Sachs on Jun 22, 2015, 2:52 pm
I am working on a project that will be able to store 175... Last reply: Maeve Donohue, Mar 20, 2023, 4:55 pm |
|
Any success with this credit yet?Pilot-Credits INpc113: Informing Design Using Triple Bottom Line Analysisposted by Sophie Kerr on Oct 29, 2018, 4:11 pmit was some how communicated to the reviewer or linked to the project. 3. Confirmation that a project member has participated in the LEED user pilot credit forum- There are only a few of us who have commented on this in the LEED User forum so my guess is not many have used this pilot credit it or it's been approved for others without participating in the forum. Log in or register to post comments Elaine Goetz Ohio University LEEDuser Basic Member July 15, 2019- 3:06 pm We also completed this credit using Autocase, but have not yet submitted it. Participating in the LEED user pilot credit forum (this posting) is one... Last reply: Rachael Johnson, Mar 20, 2023, 1:05 pm |
|
Switch Optimize Process Water use V4.1CS-v4.1 WEc3: Optimize Process Water Useposted by Michaël Briffaz on Dec 12, 2022, 8:22 am
Hi Everyone, For a C&S project in LEED V4, I'm thinking to switch "Cooling Tower Water" in V4.1 "Optimize... Last reply: Marelle Davey, Mar 20, 2023, 12:38 pm |
|
Outdoor Water Use credit- LEED V4.1NC-v4.1 WEc1: Outdoor water use reductionposted by Maria Farah on Mar 17, 2023, 12:57 pm
In LEED BD+C: New Construction V4.1, the outdoor water use reduction credit (2 points) states that alternative water sources can be used to achieve an additional 30% reduction. However, unlike in... |
|
Door operation infiltrationCS-v4 EAp2: Minimum Energy Performanceposted by Julio Fernandez Amodia on Mar 9, 2023, 11:47 am
Dear all, I am currently carrying out an energy performance calculation of a mall building for LEED minimum energy performance compliance. As with most malls, there are large number of... Last reply: Tyler Thumma, Mar 17, 2023, 11:42 am |
|
Glare control devices for residential projectsNC-v4 EQc7: Daylightposted by Sana Hafsa on Mar 17, 2023, 8:48 am
I have a residential project aiming for certification under LEED v4 NC BD+C (the buildings are over 8 floors). The Daylight credit includes "Provide manual or automatic (with manual override)... |
|
DES SystemsNC-v4 EAp2: Minimum Energy Performanceposted by Charalampos Giannikopoulos on Mar 16, 2023, 7:00 am
Dear LEEDUser friends, for a project with district systems where Option 1, Path 1 will be implemented how will be the HVAC efficiencies for the proposed model defined? Appendix G, G3.1.1.1... Last reply: Marcus Sheffer, Mar 16, 2023, 1:07 pm |
|
Entire floor area counts if at least 75% has a view?NC-v4 EQc8: Quality Viewsposted by Martha Norbeck on Mar 15, 2023, 10:55 pm
The v2009 view credit included this provision: "For private offices, the entire floor area of the office may be counted if 75% or more of the area has a direct line of sight to perimeter... Last reply: Gustavo De las Heras Izquierdo, Mar 16, 2023, 11:52 am |
|
More challenging than anticipatedPilot-Credits IPpc93: Prevention through designposted by Megan Leslie on Dec 6, 2018, 1:36 pm
I have three projects that are pursing this Pilot Credit. The project teams have found completing the worksheet more challenging than anticipated, but I think it was a useful process to go... Last reply: Stacey Flint, Mar 16, 2023, 11:51 am |