Log in
Forum
Topic

On-site Renewable Energy

Warehouses-NC-v4 EAc5: Renewable energy production
posted by Salomee Hinque on Apr 3, 2023, 11:47 pm

Hi all, 

For a new construction warehouse project, going for LEED Platinum and LEED Zero Carbon:

This new construction is build next to an existing building under the same owner....

Last reply: Marcus Sheffer, Apr 5, 2023, 11:45 am

MEP-Calculator for LEED ID+C

CI-v4 EAc2: Optimize Energy Performance
posted by Rajat Wadhwa on Apr 4, 2023, 10:29 am

For MEP Calculator when Inputting the capacity of the chiller and...

Last reply: Rajat Wadhwa, Apr 5, 2023, 11:38 am

Water Feature Include or Exclude?

EBOM-v4.1 WEc1: Water Performance
posted by Summer Minchew on Apr 5, 2023, 10:13 am

Has anyone had experience with including vs excluding site water features (fountains)?

The Reference guide "Guidance" section states, "This prerequisite allows you to understand how much...

Interior Project Water Performance

EBOM-v4.1 WEc1: Water Performance
posted by yingling guan on Aug 29, 2022, 5:56 am

For interior project, if there is only one pantry faucet within the project scope.  And occupants of this project will use other indoor water fixtures or fittings installed out of the this...

Last reply: Summer Minchew, Apr 5, 2023, 9:59 am

Equations and calc methods

EBOM-v4.1 WEc1: Water Performance
posted by Ricardo Filho on Feb 21, 2023, 4:55 am

hi all, 

I am doing some research on the LEED v4.1 O+M and I came across some questions regarding this credit. Anyone has any idea about possible answers?
 

Water efficiency...

Last reply: Summer Minchew, Apr 5, 2023, 9:50 am

Retail basline HVAC

CS-v4 EAc2: Optimize Energy Performance
posted by Julio Fernandez Amodia on Apr 3, 2023, 6:41 am

Hi to all,

I am currently carrying out an energy model for a mall building and assigning the baseline HVAC systems to the zones. I am confused about the retail units, there are hundreds of...

Last reply: Marcus Sheffer, Apr 4, 2023, 8:48 am

Modeling DHW system for CI project

CI-v4 EAc2: Optimize Energy Performance
posted by Rajat Wadhwa on Apr 3, 2023, 10:31 am

Hi, 

I am trying to model the baseline...

Last reply: Marcus Sheffer, Apr 3, 2023, 2:31 pm

FTE for Data center

Data-Centers-NC-v4 LTc6: Bicycle facilities
posted by Carlos Bueno on Apr 3, 2023, 10:29 am

What would be the correct...

Nuclear Power

NC-v4 EAc7: Green power and carbon offsets
posted by Kelsey Lenhoff on Jun 9, 2020, 8:27 pm

Is Nuclear Power ever considered to be a Green Power or Carbon Offset source especially in the eyes of LEED? I highly doubt it, but I have recieved conflicting information from a client and...

Last reply: Marcus Sheffer, Apr 3, 2023, 9:26 am

IPc101- Integrative Process- good practice

Pilot-Credits IPpc101: Integrative process
posted by Kelvin Chan on Apr 2, 2023, 3:13 am

It is recommended to set up an integrative team with all stakeholders at the early stage, prior to commencement of the project, the team shall establish an Integrative Process (IP) Team. The IP...