Strategy for Project surrounded by Active Non-LEED Construction & Dirt Roads
NC-v4 SSp1:Construction activity pollution preventionposted by A&L SUSTENTABILIDADE on
I am looking for advice on best strategy to comply with this prerequisite, since it's a unique site condition.
Contractor Declaration template
NC-v4 SSp1:Construction activity pollution preventionposted by Summer Gorder on
Does anyone have an example Declaration form tat complies with the documentation option below, if the GC can't locate photos:
Activity Pollution Prevention Plan
NC-v4 SSp1:Construction activity pollution preventionposted by Heloise Gaza on
Hello,
LEED equivalencies with German Regulation and construction practices.
NC-v4 SSp1:Construction activity pollution preventionposted by Carlos Cura on
Has ther been a study or comparative analysis of German local regulations or equivalences to LEED criteria.
For example,
Sediment-laden runoff/Non compliance with IEPA permit - reporting
NC-v4 SSp1:Construction activity pollution preventionposted by Taylor Gawthorp-Cruse on
The project has an ECS plan in place for construction, silt fences etc.
Need a Template or format for preparation of ESC Plan
NC-v4 SSp1:Construction activity pollution preventionposted by Mujib ur Rehman on
Dear All,
Frequency of inspections
NC-v4 SSp1:Construction activity pollution preventionposted by Maria Porter on
We got a review comment: “Provide additional documentation to confirm that the project meets the requirements for reductions in inspection frequency (Section 4.1.4 of the EPA Construction Gener
Should archaeological works, taking place before construction start, be included in ESC Plan?
NC-v4 SSp1:Construction activity pollution preventionposted by Agata Mozer on
Dear All,
Wastewater from Concrete Washout facility
NC-v4 SSp1:Construction activity pollution preventionposted by Osman Faroq on
Dear All,
Local Standards Comparisons as Required Documents
NC-v4 SSp1:Construction activity pollution preventionposted by Nate Shroyer on
When working on a project using local standards rather than the 2012 EPA CGP, what is necessary to prove that the local standards are as, if not more, stringent than the CGP. How in depth doe
Plan de Contrôle d'Erosion & Sedimentation / Storm Water Prevention Plan
NC-v4 SSp1:Construction activity pollution preventionposted by saif eddine majdaoui on
Does the monitoring of SWPP and PCES have to be carried out every week on LEED certification projects even if in the absence of rainy / weather events (No precipitation / no rain)
What's considered substantial completion if building is completed before the site?
NC-v4 SSp1:Construction activity pollution preventionposted by Adam Huckstep on
Hi All, I have a question on how to handle a project where construction will continue after the projects building is complete and ready for occupancy.
SSP1 scope
NC-v4 SSp1:Construction activity pollution preventionposted by Adam Insan on
Hi,
We are working on LEED project as general contractor in middle east which is registered under LEED new construction.
Zero lot line Definition
NC-v4 SSp1:Construction activity pollution preventionposted by Alex Edwards on
Hi All!
Soil stockpiling over the winter
NC-v4 SSp1:Construction activity pollution preventionposted by Scott Beckman on
We have a correctional project where we are doing some of the sitework now but the project work will be paused over the winter.
Perimeter Control: is it necessary?
NC-v4 SSp1:Construction activity pollution preventionposted by Victoria Rios Esteve on
Hi everyone!
LEED Consultants working in remote mode.
NC-v4 SSp1:Construction activity pollution preventionposted by Olga Yuil on
As LEED Consultants we are working in remote mode because of COVID-19 risk.
The Project Team is concern about how this may or may not affect the certification.
IECA vs US EPA CGP
NC-v4 SSp1:Construction activity pollution preventionposted by Gregory Mason on
Hi,
Different contractors for earthworks and construction
NC-v4 SSp1:Construction activity pollution preventionposted by Vanessa Montezuma Ramos on
Hi everyone,
Chilled Water rinsing / cleaning - How to ensure safe disposal ?
NC-v4 SSp1:Construction activity pollution preventionposted by Amine Zeidane on
Hello LEED Community,
Project Zero Lot Line with Major Renovation
NC-v4 SSp1:Construction activity pollution preventionposted by Victoria Rios Esteve on
Hi everyone!
When is a CAPP Plan not a LEED conforming Plan?
NC-v4 SSp1:Construction activity pollution preventionposted by Harry Flamm on
We are building a high-rise residential building in a tight urban (Boston) site that is under 1-acre in size.
EPA CGP 2003/2012
NC-v4 SSp1:Construction activity pollution preventionposted by Charalampos Giannikopoulos on
Hi all! Is anyone aware of a table summarizing the changes that were introduced by EPA CGP 2012 when compared to the 2003 version?
Missing inspection documentation
NC-v4 SSp1:Construction activity pollution preventionposted by Sean Adams on
Project has always been trying to earn LEED Silver and ESC plan was in place since beginning of construction but we have limited photo/inspection documentation.
Construction Activity pollution prevention inspections
NC-v4 SSp1:Construction activity pollution preventionposted by Irene Carreno on
Hello. I am working in a project that has the Erosion and control plan following the CGP 2012(LEED V4) , part of the plan is to have weekly inspections on site to review how the erosion and control
monitoring frequency of Storm Water Prevention Plan
NC-v4 SSp1:Construction activity pollution preventionposted by saif eddine majdaoui on
Does the monitoring of SWPP and PCES have to be carried out every week on LEED certification projects even if in the absence of rainy / weather events (No precipitation / no rain
ESC Plan For A Warehouse Project
NC-v4 SSp1:Construction activity pollution preventionposted by Jourdan Younis on
Hello,
Too late for SSp1?
NC-v4 SSp1:Construction activity pollution preventionposted by André Harms on
A potential LEED project in Addis Ababa, Ethiopia, had already begun demolition and some construction activities before a LEED AP was appointed.
Stormwater Management in a project without pre-existing infrastructure
NC-v4 SSp1:Construction activity pollution preventionposted by Amine Zeidane on
Hello,
I'm working on a mixed-use tower construction project in Morocco.
Hoarding dimensions
NC-v4 SSp1:Construction activity pollution preventionposted by Ahmed Labeeb on
Dear All,
Is there any LEED requirement regarding the hoarding dimensions ( distance from ground to the bottom of the panel)?
Compliance in early construction
NC-v4 SSp1:Construction activity pollution preventionposted by ARDOR GREEN on
Dear all,
Substantial differences between the CGP from 2012 as required in LEED V4?
NC-v4 SSp1:Construction activity pollution preventionposted by veronica oyarzun on
Can anyone please tell me how different should be documenting this credit comparing with LEED 2009?
Acceptable Measures to avoid discharges of fuel
NC-v4 SSp1:Construction activity pollution preventionposted by Instra Ingenieros on
The CGP 2020 specify the next in the section 2.3.1. Prohibited Discharges " 2.3.1.3 Fuel, oils or other pollutans used in vehicle and equipment operation and maintenance.
CAPP Plan
NC-v4 SSp1:Construction activity pollution preventionposted by UGC/GPRO Office Account on
Hello, Does anyone have a Construction Activity Pollution Prevention plan example? What does it include? Erosion control, light pollution prevention, stormwater management plan
ESC plan
NC-v4 SSp1:Construction activity pollution preventionposted by Ana Paula Quiros on
Hello, There is a hotel that might look certification and has 2 floors already built, then the construction stopped and they want to add now 3 more floors.
ESC plan for major renovation of data center
NC-v4 SSp1:Construction activity pollution preventionposted by sean wang on
Here is a major renovation project for data center. Only structure reinforcement is required for major renovation.
Applicability within campus boundary limits
NC-v4 SSp1:Construction activity pollution preventionposted by Samer Alhmdan on
Hello, I have multiple buildings within a campus, do we need to implement this prerequisite within the whole campus boundaries, or only within buildings LEED boundaries, noting that there are some
ESC plan for major renovation of data center
NC-v4 SSp1:Construction activity pollution preventionposted by sean wang on
We met a confused case. As it is a major renovation for data center, there is no need for controlling soil erosion, waterway sedimentation for construction.
EPA New Version
NC-v4 SSp1:Construction activity pollution preventionposted by Jennifer Webb on
The EPA has issued the 2017 Construction General Permit (see web page https://www.epa.gov/npdes/stormwater-discharges-construction-activities-2017-cgp) that became effective on February 16, 2017.
Erosion and Sedimentation Measures during demolition
NC-v4 SSp1:Construction activity pollution preventionposted by Anaïs P on
During demolition works, should the Erosion and Sedimentation measures be implemented? The Reference Guide only refers to construction works...