Here is a major renovation project for data center. Only structure reinforcement is required for major renovation. No controlling soil erosion, waterway sedimentation required, could you please advise how to meet this prerequisite?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Karin Miller
Senior Sustainability ManagerYR&G
33 thumbs up
July 31, 2015 - 3:07 pm
Sean,
All projects are required to create an erosion and sedimentation control plan, the plan will differ between projects with significant site areas, and those with a zero lot line. There are useful references for the types of strategies you might consider including in the v2009 forum here:
http://www.leeduser.com/credit/NC-2009/SSp1#bev-tab
Karin