I've never been in this situation before, and I don't want to hit the button and 'wait and see.' i have a project where we were doing a split submittal. I submitted for preliminary design review and received comments. That review garnered several pending credits that we need to do clarifications on. None are currently denied.
The clarifications took longer than expected to get back from my consultants, and in that time, construction was completed. The construction credits are now complete and ready to go. In light of that, I would prefer not to submit the clarifications to the pending design review credits only and wait another 3-4 weeks for those to come back. I want to submit those and the construction credits all together and just get going on the remainder of the review.
So, can I do this by pressing the 'skip review' button under Design Final Review? Does it automatically kick those design credit that are re-opened and clarified to the next phase, Construction Review? I don't want to press the skip button and somehow the pending credits get put in as final or denied without the proper clarification and review.
Thanks.
Add new comment
To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.