LEED project with associated Parking DeckNC-v4 MPR2: Must use reasonable LEED boundariesposted by Ashley Love on Aug 25, 2016, 5:35 pm
I have a question concerning LEED projects with associated parking decks. If this question has been answered elsewhere, I have not been able to find it, so please point me in the direction! I... Last reply: Tristan Roberts, Jan 17, 2017, 1:12 pm |
|
Greenguard Gold, SCS Indoor Advantage Gold?NC-v4 EQc2: Low-emitting materialsposted by Erin Holdenried on Dec 22, 2016, 4:27 pm
Do these certifications meet the requirements for furniture? Last reply: Michelle Halle Stern, Jan 17, 2017, 12:41 pm |
|
Apartment flush-outNC-v4 EQc4: Indoor air quality assessmentposted by Mike Henderson on Nov 30, 2016, 1:20 pm
I'm not an engineer or designer, but I have a question related to a new apartment I just moved in to. The building is new construction, and only the 4th floor (top floor) is completed. I was able... Last reply: Tristan Roberts, Jan 17, 2017, 12:27 pm |
|
SFI vs FSCNC-v4 MRc3: Building product disclosure and optimization - sourcing of raw materialsposted by Leanne Conrad on Nov 28, 2016, 3:57 pm
Does anyone know if... Last reply: Tristan Roberts, Jan 17, 2017, 12:15 pm |
|
IN: Green Building EducationEBOM-v4 INc1: Innovationposted by Alexa Stone on Jan 17, 2017, 8:44 am
One of the elements of this credit includes: The development of a manual, guideline or case study to inform the design of other buildings based on the successes of this project. For an O+M... Last reply: Trista Brown, Jan 17, 2017, 11:42 am |
|
New to LEED SubmitalsLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Joel Clonch on Jan 16, 2017, 5:15 pm
I have a mill-work submittal that requests : Last reply: Martha Norbeck, Jan 17, 2017, 9:31 am |
|
Option 1 Path 2 – monitoring-based Cx – how far to go?Schools-NC-v4 EAc1: Enhanced Commissioningposted by Tom Kennedy on Jan 11, 2017, 3:19 pm
My customer will build a new K-12 school building using LEED V4. We are in the planning stages and they have expressed interest in monitoring-based... Last reply: Scott Bowman, Jan 16, 2017, 12:40 pm |
|
Pilot ProgramEBOM-v4 EAp2: Minimum Energy Performanceposted by Meier Corporate Account on Dec 5, 2016, 1:55 pm
Good Afternoon, We cannot complete the existing credit as we cannot meet any of the Cases / Options. There is no Energy Star rating for dairies... (While they are trialing one, it is not... Last reply: Tristan Roberts, Jan 15, 2017, 1:19 pm |
|
EBOM 2009 IEQ3.2 Alternative Compliance PathEBOM-2009 IEQc3.2: Green cleaning - custodial effectiveness assessmentposted by Kimberly Hosken on Jun 13, 2016, 3:27 pm
Our project is a five story public building with operational contracts which include "contract document requirements". These are essentially a series of reports that must be provided per the... Last reply: Tristan Roberts, Jan 15, 2017, 10:32 am |
|
URGENT- Eligibility Advice needed right away!NC-v4 MPR2: Must use reasonable LEED boundariesposted by Erica Downs on Dec 15, 2016, 9:50 pm
If anyone can, I need an answer ASAP -- The project will be a new-construction Concrete Manufacturing Plant. The City is requiring LEED certification, but I'm not sure the project would... Last reply: Deborah Lucking, Jan 13, 2017, 2:28 pm |