Seasonal Commissioning

NC-v4 EAc1:Enhanced commissioning
posted by  komal m  on 

Is seasonal commissioning required or optional for proejcts? Is seasonal commisioning applicable for tropical areas, as there is hardly any seasonal variation observed throughout the year?

0

FSC Invoices, Chain of Custody, and Certified Wood Cost

CI-2009 MRc7:Certified Wood
posted by  Eric Thompson  on 

I'm working on a project in Norway and I'm somewhat confused about the documentation for Certified Wood. The Reference Guide states: Collect all *vendor* invoices for permanently installed wood p

2
Architect / Sustainability Strategist
Perkins+Will
LEEDuser Basic Member
161 thumbs up
Thu Nov 17, 2022, 12:53 am

Area used in calculation?

NC-v4 LTc7:Reduced parking footprint
posted by  Dave Hubka  on 

When registering a project in LEED Online the gross floor area is used. Gross floor area is calculated from the exterior walls. https://usgbc.org/glossary#gross-floor-area-gfa

2
Wed Nov 16, 2022, 7:27 pm
14
Principal | Director of Sustainability & Building Performance
Arrowstreet
LEEDuser Basic Member
1 thumbs up
Wed Nov 16, 2022, 5:32 pm

Hazardous ingredients

NC-v4.1 MRc4:Material Ingredients
posted by  Aleksandra Suchomska  on 

If a manufacturer provides an inventory of all potentially hazardous ingredients (up to 100ppm) but omits ingredients that pose no risk and does not list them, does the report qualify for Option 1

1
Wed Jun 14, 2023, 3:18 pm

LEED ND GIBp1 - WELL Building Certification

ND-v4 GIBp1:Certified green building
posted by  Jennifer Bryant  on 

Would certification of buildings within the masterplan under the IWBI's WELL Building Standard V2 be sufficient to fulfil the requirements of this credit?

0
1
Fri Dec 16, 2022, 1:11 pm

Cx scope for ventilation, air conditioners of the base building

CI-v4 EAp1:Fundamental commissioning and verification
posted by  Michael   on 

My store project is located inside a big department store in Japan. All HVAC system in my project is controlled by the landlord of the base building.

0

Data cabling and carpet quantity difficulty

Pilot-Credits MRpc132:Procurement of Low Carbon Construction Materials
posted by  Deb Favaretto  on 

The language of the Pilot Credit now requires Communications (data cabling). 

1
Fri Aug 30, 2024, 6:21 pm