Items that are used for either MRc4 or MRc3

NC-2009 MRc4: Recycled Content
posted by Erika Duran on Mar 24, 2015, 4:26 pm

reach thresholds for Reuse Credits MRc1 or MRc3, It CAN count reused material from the jobsite as diverted construction waste under MRc2. Michelle & Tristan made relevant posts in the MRc2 forum...

Last reply: Tristan Roberts, Mar 14, 2016, 2:37 pm

Re-commisioning

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by John Wood on Mar 9, 2016, 7:08 am

I am a PE who has been approached by a building owner with a request to have the building "re-commissioned." I have designed LEED projects before, and participated in the original...

Last reply: John Wood, Mar 14, 2016, 2:15 pm

Prescriptive Method of Documenting- Floor Area (per bay)

NC-2009 IEQc8.1: Daylight and views - daylight
posted by Michael Haugh on Mar 10, 2016, 6:28 pm

First off, I have had a very hard time finding information to help complete this Credit's documentation. There are terms that are undefined or have one meaning in regards to this Credit but other...

Last reply: TODD REED, Mar 14, 2016, 2:09 pm

pc14 for Historic School building in urban context

Pilot-Credits PC14: Walkable Streets
posted by Kristian Whitsett on Mar 11, 2016, 10:58 am

We were inspired to test out this credit because of the huge increase in students walking to school after we completed a full renovation of a historic school in North Adams, MA. Close...

NC-v4 LTc2: Sensitive land protection/Wetland Protection

NC-v4 LTc2: Sensitive land protection
posted by Robyn Dowsey on Nov 20, 2014, 11:10 am

Is there a precedent anywhere for getting this credit with...

Last reply: Blake Jackson, Mar 11, 2016, 10:05 am

What areas to include for planted areas?

NC-2009 WEc1: Water Efficient Landscaping
posted by Lauren Bellamy on Mar 1, 2016, 8:46 am

We have a project where only about 1/3 of the planted area will be irrigated. The other 2/3 is planted with plants and groundcover that will not require irrigation.

Do we just include the...

Last reply: Karin Miller, Mar 10, 2016, 4:51 pm

Option 2

NC-v4 SSc4: Rainwater management
posted by henry nguyen on Jan 20, 2016, 6:16 pm

Hello, I wonder how should I understand Opt.2 BD+C
Rain water Mgmt credit.
"Manage on site the annual increase in runoff volume from the natural land cover condition to the post-...

Last reply: Michael DeVuono, Mar 10, 2016, 11:25 am

Daylight and Views- RP For Earning 1 Point For Just Daylight?

EBOM-2009 RPc1: Regional Priority
posted by Michelle Bracewell-Musson on Nov 21, 2015, 11:15 am

Hello,

To earn EP, a project must earn 75% for Daylight AND 90% for Views. For Regional Priority, can it just be meeting the 50% of only DAYLIGHT, to earn the Regional Priority point? I...

Last reply: Trista Brown, Mar 9, 2016, 11:08 pm

93727 On-site & Off-site Ren. En.- RP for 6 Points if only Off?

EBOM-2009 RPc1: Regional Priority
posted by Michelle Bracewell-Musson on Nov 21, 2015, 10:52 am

Hello,

I know that a project can only earn Exemplary if 100% is off-set, however, it must be a COMBINATION of On-site and Off-site to earn EP. :(
Is the Regional Priority point the...

Last reply: Trista Brown, Mar 9, 2016, 11:03 pm

Residents excluded?

EBOM-2009 SSc4: Alternative Commuting Transportation
posted by Miranda Lescaze on Feb 23, 2015, 3:14 pm

A portion of our building is office space and a portion is multi-family senior residences. The alternative commuting survey guidance seems to refer to, and make sense to, implementation for the...

Last reply: Trista Brown, Mar 9, 2016, 7:46 pm