Option 2

Hello, I wonder how should I understand Opt.2 BD+C Rain water Mgmt credit. "Manage on site the annual increase in runoff volume from the natural land cover condition to the post-developed condition." Does that mean that I should design the site so that it can help increase annual runoff volume and stays in such condition all the way thru post-developed condition, given the base line is "natural land cover condition" ?

1

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 01/20/2016 - 23:33

Option 2 Post Development Volume - Pre Development Volume = Volume to be Managed

Thu, 01/21/2016 - 01:20

Thank you Michael, it's much clearer the way you said it.

Thu, 03/10/2016 - 16:07

Hi, I am not sure about the definition of "natural land cover condition" and which predevelopment conditions should be used. If the pre Development site, for example, is a parking lot, the Pre Development Volume is the volume from parking lot or from the same site before any land modification was undertaken "Natural"? Thank you.

Thu, 03/10/2016 - 16:25

Natural Condition = What your site was in the Stone Age, before it was touched by man.