Hello,

I know that a project can only earn Exemplary if 100% is off-set, however, it must be a COMBINATION of On-site and Off-site to earn EP. :(
Is the Regional Priority point the same, where we MUST have On-site? Meaning, if we purchase 62.5% (4 points) of ONLY Off-site, will we earn the point or can it only work for On-site (7.5%)? We have solar on-site, however, the Owner doesn't own the REC's, therefore, it is my understanding we cannot take credit for any of the on-site generated solar power, so the plan is to purchase 100% (two year contract).

Thank you for your time!