Topic

Erosion and Sedimentation Measures during demolition

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by Anaïs P on Feb 9, 2016, 10:49 am

During demolition works, should the Erosion and Sedimentation measures be implemented?
The Reference Guide only refers to construction works...

Last reply: Tristan Roberts, Feb 22, 2016, 12:21 pm

ESC plan for major renovation of data center

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by sean wang on Jul 27, 2015, 1:52 am

We met a confused case. As it is a major renovation for data center, there is no need for controlling soil erosion, waterway sedimentation for construction. Only...

Last reply: Tristan Roberts, Feb 9, 2016, 12:33 pm

ESC plan for major renovation of data center

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by sean wang on Jul 27, 2015, 2:01 am

Sean, All projects are required to create an erosion and sedimentation control plan, the plan will differ between projects with significant site areas, and those with a zero lot line. There are useful references for the types of strategies you might consider including in the v2009 forum here: http://www.leeduser.com/credit/NC-2009/SSp1#bev-tab Karin Log in or register to post comments 0 Vote up! ...

Last reply: Karin Miller, Jul 31, 2015, 3:07 pm

CAPP Plan

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by UGC/GPRO Office Account on Feb 14, 2014, 2:34 pm

Hello,

Does anyone have a Construction Activity Pollution Prevention plan example? What does it include? Erosion control,...

Last reply: Tristan Roberts, Mar 7, 2014, 11:11 am