Quality views in nonregularly occupied spacesNC-v4 INc1: Innovationposted by keerthana gopi on Feb 27, 2019, 8:41 am
One of our projects is a 30-storey building. The credit requires 15% of non regularly occupied floor area to have access to views. Is there any expected pattern for floor-wise distribution or can... |
|
Development density of the surrounding residential zone or neighborhood (units/hectare) CALCULATION.CS-2009 SSc2: Development Density and Community Connectivityposted by Guillermo Hernandez Espinoza on Mar 1, 2019, 4:20 pm
Hi, we are pursuing the option 2 and we have no problems selecting the 10 basic services within a 1/2 mile since we are located on an urban core area. |
|
BAS required for strategy "C. CO2 Monitoring"NC-v4 EQc1: Enhanced indoor air quality strategiesposted by Gustavo De las Heras Izquierdo on Mar 3, 2019, 5:24 pm |
|
Stormwater ManagementNC-2009 SSc6.1: Stormwater design - quantity controlposted by Divantha Ekanayake on Mar 4, 2019, 12:10 am
The project I’m referring to is a LEED 2009 New Construction project, and has already been sent for the design review and received back with review comments. Under the Storm Water design-... |
|
ID+C Retail: Shared Outdoor air clarificationRetail-CI-v4 EQp1: Minimum indoor air quality performanceposted by Mahesh Shankar on Mar 5, 2019, 12:39 am
Hi all, The project is a retail store in Taiwan. The... |
|
Rainwater managementNC-v4 SSc4: Rainwater managementposted by Amr Elkranfely on Mar 5, 2019, 5:18 am
Now I'm working on a project located in a very hot climate country and arid region. The nature of the land their is a natural desert where water scarcity is a big challenge to the country. The... |
|
Steam to Hot Water Heat Exchanger MeteringNC-v4 WEp3: Building-level water meteringposted by Greg DiDomenico on Mar 11, 2019, 12:40 pm
Hello all, I am working on a project on a site that has district energy. The two utilities supplied to the building are chilled water and high pressure steam. Both of these... |
|
Flush Out Path 2- Fitness center/ OfficeNC-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Crina Bosch on Mar 11, 2019, 4:30 pm
I am working on a fitness center project and the team would like to follow Enhanced Commisioning Path 2: Flush-out. This option allows the building to be occupied prior to completion of... |
|
Reuse furniture costCI-v4 MRc2: Interiors life-cycle impact reductionposted by pradeep kumar on Mar 12, 2019, 2:13 am
We are doing the project in which our client reusing the furniture from their existing office to the new office. Furniture comprises of wooden tables, chairs etc. How could we identify the cost... |
|
Does low-emitting and fuel efficient vehicles parking count as preferred parking?CI-v4 LTc5: Reduced parking footprintposted by Ameet AA on Mar 13, 2019, 3:43 am
Hi, Our project has a few parking spaces reserved for low-emitting and fuel efficient vehicles, does it count as preferred parking? Thanks. |